Construction unit costs in Duval County, FL

Median awarded unit prices for 69 items on public projects in Duval County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Duval County

ItemPerMedianMiddle halfWinning bidsLatest source document
Paint pavement markinglinear foot$2.49$1.85 – $3.20103Aug 26, 2026, Open bid tab, T2A78 ↗
Thermoplastic, Standard, Whitelinear foot$6.50$5.00 – $9.0099Aug 26, 2026, Open bid tab, T2A78 ↗
Milling Existing Asphaltsquare yard$5.00$3.19 – $6.9994Aug 26, 2026, Open bid tab, T2A78 ↗
Raised Pavement Marker, Type Beach$5.20$5.00 – $6.5069Aug 26, 2026, Open bid tab, T2A78 ↗
Thermoplastic, Standard, Whiteeach$137.03$95.00 – $200.0061Aug 26, 2026, Open bid tab, T2A78 ↗
Concrete Sidewalk andsquare yard$91.62$72.70 – $123.2550Aug 26, 2026, Open bid tab, T2A78 ↗
Thermoplastic, Preformedeach$228.00$152.00 – $318.7550Jul 29, 2026, Open bid tab, T2A29 ↗
Paint pavement markingeach$60.00$49.00 – $85.0049Aug 26, 2026, Open bid tab, T2A78 ↗
Asphalt Concrete Frictionton$225.44$197.92 – $264.1739Aug 26, 2026, Open bid tab, T2A78 ↗
Guardrail Transition Connectioneach$3,500$2,998 – $4,05039Aug 26, 2026, Open bid tab, T2A78 ↗
Conduit, Furnish & Installlinear foot$37.50$29.70 – $48.0037Aug 26, 2026, Open bid tab, T2A78 ↗
Prestressed Concrete Pole, F&Ieach$2,222$1,806 – $3,00035Mar 25, 2026, Open bid tab, T2A65 ↗
Litter removeacre$140.10$96.00 – $312.5035Aug 26, 2026, Open bid tab, T2A78 ↗
Mowingacre$218.80$117.50 – $391.5934Aug 26, 2026, Open bid tab, T2A78 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,585$1,458 – $1,71334Aug 26, 2026, Open bid tab, T2A78 ↗
Conduit, Furnish & Install, Openlinear foot$21.88$17.00 – $31.0034Aug 26, 2026, Open bid tab, T2A78 ↗
Temporary Barrier, Relocatelinear foot$15.00$12.00 – $17.5033Jul 29, 2026, Open bid tab, T2A29 ↗
Inlet Protection Systemeach$200.00$128.75 – $226.0032Aug 26, 2026, Open bid tab, T2A78 ↗
Remove of existing concretesquare yard$50.00$37.21 – $82.5032Aug 26, 2026, Open bid tab, T2A78 ↗
Superpave asphalt concreteton$207.45$184.25 – $243.4432Aug 26, 2026, Open bid tab, T2A78 ↗
Performance Turf, Sodsquare yard$9.35$4.46 – $19.2532Aug 26, 2026, Open bid tab, T2A78 ↗
Vehicle Detection Systemeach$12,500$11,092 – $19,67931Mar 25, 2026, Open bid tab, T2A65 ↗
Electrical Service Wire, Furnishlinear foot$9.35$7.08 – $11.5431Mar 25, 2026, Open bid tab, T2A65 ↗
Embankmentcubic yard$57.95$32.25 – $99.5930Jun 10, 2026, Open bid tab, T2A47 ↗
Thermoplastic, Standardlinear foot$6.00$5.50 – $7.0030Aug 26, 2026, Open bid tab, T2A78 ↗
Thermoplastic, Preformedlinear foot$15.00$14.00 – $20.0030Mar 25, 2026, Open bid tab, T2963 ↗
Traffic Control Officerhour$105.00$95.00 – $125.0029Aug 26, 2026, Open bid tab, T2A78 ↗
Electrical Service Disconnecteach$1,484$1,150 – $2,02228Aug 26, 2026, Open bid tab, T2A78 ↗
Guardrail -Roadway, General TL-3linear foot$28.35$25.70 – $32.0827Aug 26, 2026, Open bid tab, T2A78 ↗
Fiber Optic Cable Locatorday$275.00$163.41 – $395.0027Jul 29, 2026, Open bid tab, T2A29 ↗
Concrete Curb & Gutter, Type Flinear foot$67.50$53.00 – $89.5027Aug 26, 2026, Open bid tab, T2A78 ↗
Detectable Warningssquare foot$45.00$40.61 – $56.7526Aug 26, 2026, Open bid tab, T2A78 ↗
Miscellaneous Asphalt Pavementton$550.57$360.53 – $700.0026Aug 26, 2026, Open bid tab, T2A78 ↗
Temporary Barrier, F&I, Lowlinear foot$48.65$37.85 – $55.0025Jan 28, 2026, Open bid tab, T2A54 ↗
Pipe Culvert,Optionallinear foot$334.00$203.25 – $750.0024Jan 28, 2026, Open bid tab, T2A56 ↗
Sediment Barrierlinear foot$3.25$1.40 – $4.5424Aug 26, 2026, Open bid tab, T2A78 ↗
Paint pavement markingsquare foot$6.30$5.00 – $10.0023Mar 25, 2026, Open bid tab, T2963 ↗
Pull & splice box, f&i, 24 inch x 36 incheach$2,720$2,533 – $3,02023Mar 25, 2026, Open bid tab, T2A65 ↗
Pedestrian Detector, Furnish &each$421.00$348.22 – $504.0023Jul 29, 2026, Open bid tab, T2A29 ↗
Pipe Culvert, Opt Materiallinear foot$450.00$250.00 – $1,09221Jan 28, 2026, Open bid tab, T2A56 ↗
Pipe Culvert, Optional Materiallinear foot$250.00$170.00 – $500.0021Aug 26, 2026, Open bid tab, T2A78 ↗
Manhole, Adjusteach$1,900$1,536 – $2,00021Aug 26, 2026, Open bid tab, T2A78 ↗
Valve Boxes, Adjusteach$1,312$1,050 – $1,70021Aug 26, 2026, Open bid tab, T2A78 ↗
Tubular marker, durable, 36 incheach$205.00$200.00 – $258.7521May 22, 2024, Open bid tab, T2979 ↗
Business Signeach$45.00$30.00 – $50.4221Aug 26, 2026, Open bid tab, T2A78 ↗
Sign Panel, Remove, up to 12 SFeach$76.88$50.00 – $126.2520Mar 25, 2026, Open bid tab, T2A65 ↗
Loop Detector Inductive, F&I,each$436.00$367.63 – $477.5020Aug 26, 2026, Open bid tab, T2A78 ↗
Steel Mast Arm Assembly, Furnisheach$81,700$75,000 – $93,63820Mar 25, 2026, Open bid tab, T2963 ↗
Object Marker, Type 1each$269.38$237.00 – $288.7520Aug 26, 2026, Open bid tab, T2A78 ↗
Aluminum signal pole, pedestaleach$3,000$2,727 – $3,40019Jul 29, 2026, Open bid tab, T2A29 ↗
Manhole, Adjust, Utilitieseach$1,800$1,537 – $2,00019Aug 26, 2026, Open bid tab, T2A78 ↗
Guardrail End Treatmenteach$3,275$3,050 – $4,24018Aug 26, 2026, Open bid tab, T2A78 ↗
Retroreflective Sign Stripeach$95.00$80.00 – $110.0017Aug 26, 2026, Open bid tab, T2A78 ↗
Type B Stabilizationsquare yard$42.00$33.50 – $75.0017Jul 29, 2026, Open bid tab, T2A29 ↗
Pedestrian Detector, Removeeach$100.47$65.00 – $157.5316Jul 29, 2026, Open bid tab, T2A29 ↗
Aluminum signal pole, removeeach$544.00$463.39 – $820.0016Mar 25, 2026, Open bid tab, T2963 ↗
Internally Illuminated Signeach$6,424$5,280 – $7,21716Jan 28, 2026, Open bid tab, T2A56 ↗
Fiber Optic Connection, Installeach$81.41$65.52 – $95.0516Mar 25, 2026, Open bid tab, T2A65 ↗
Aluminum signal pole, furnish &each$2,797$2,252 – $3,02516Jul 29, 2026, Open bid tab, T2A29 ↗
Regular Excavationcubic yard$48.00$37.00 – $75.0015Jun 10, 2026, Open bid tab, T2A47 ↗
Borrow Excavation, Truckcubic yard$57.50$46.25 – $80.0514Aug 26, 2026, Open bid tab, T2A78 ↗
Fiber Optic Cable, F&Ilinear foot$4.43$4.00 – $5.7314Mar 25, 2026, Open bid tab, T2A65 ↗
Delineator, Flexible Tubulareach$125.00$105.00 – $150.0013Jul 29, 2026, Open bid tab, T2A29 ↗
Traffic Separator Concretelinear foot$83.24$54.84 – $177.5012Mar 25, 2026, Open bid tab, T2963 ↗
Mitered End Section, Optionaleach$3,750$3,146 – $5,00012Aug 26, 2026, Open bid tab, T2A78 ↗
Managed Field Ethernet Switcheach$4,607$4,155 – $5,07412Mar 25, 2026, Open bid tab, T2A65 ↗
Guardrail removelinear foot$3.30$2.50 – $10.3512Aug 26, 2026, Open bid tab, T2A78 ↗
Optional Base, Base Group 09square yard$97.50$80.00 – $131.5312Jul 29, 2026, Open bid tab, T2A29 ↗
Concrete Curb & Gutter, Type Elinear foot$68.00$44.08 – $75.7512Aug 26, 2026, Open bid tab, T2A78 ↗