Street Lighting · awarded bid prices · Broward County
Electrical Service Disconnect: cost per each in Broward County, FL
The median awarded price is $1,986 per each, from 36 winning bids on 21 public projects in Broward County, FL (2024–2026). Half of the awarded prices fall between $813.04 and $3,805.
Cost by state › Florida › Broward County › Electrical Service Disconnect
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1,697 in 2019 to $1,971 in 2025 (+16%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $1,697 | 6 |
| 2021 | $1,683 | 12 |
| 2022 | $2,521 | 5 |
| 2024 | $2,420 | 17 |
| 2025 | $1,971 | 15 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 2 EA | $1,871 | Open bid tab, T4757 ↗ |
| Jun 10, 2026 | FDOT | 2 EA | $405.01 | Open bid tab, T4766 ↗ |
| Mar 25, 2026 | FDOT | 2 EA | $756.64 | Open bid tab, T4734 ↗ |
| Mar 25, 2026 | FDOT | 1 EA | $2,850 | Open bid tab, T4753 ↗ |
| Dec 3, 2025 | FDOT | 6 EA | $2,300 | Open bid tab, T4717 ↗ |
See every awarded price for this item on the Electrical Service Disconnect item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $24.23 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Light Pole Complete, F&I: $11,000 per each
- Lighting Conductors, F&I: $4.95 per linear foot
- Electrical Service Wire, Furnish: $11.71 per linear foot
- Pole Cable Distribution System: $915.00 per each