Street Lighting · awarded bid prices · Broward County
Conduit, Furnish & Install, Open: cost per linear foot in Broward County, FL
The median awarded price is $24.23 per linear foot, from 52 winning bids on 28 public projects in Broward County, FL (2023–2026). Half of the awarded prices fall between $19.16 and $30.00.
Cost by state › Florida › Broward County › Conduit, Furnish & Install, Open
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $14.00 in 2020 to $24.01 in 2025 (+71%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2020 | $14.00 | 9 |
| 2021 | $11.04 | 20 |
| 2022 | $15.59 | 20 |
| 2023 | $30.00 | 15 |
| 2024 | $24.65 | 23 |
| 2025 | $24.01 | 24 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 32266 LF | $10.75 | Open bid tab, T4757 ↗ |
| Jun 10, 2026 | FDOT | 31 LF | $19.12 | Open bid tab, T4766 ↗ |
| Jan 28, 2026 | FDOT | 463 LF | $18.31 | Open bid tab, T4749 ↗ |
| Dec 3, 2025 | FDOT | 334 LF | $22.00 | Open bid tab, T4717 ↗ |
| Sep 24, 2025 | FDOT | 244 LF | $28.00 | Open bid tab, T4721 ↗ |
The same item across Florida: statewide figures. See every awarded price for this item on the Conduit, Furnish & Install, Open item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Light Pole Complete, F&I: $11,000 per each
- Lighting Conductors, F&I: $4.95 per linear foot
- Electrical Service Disconnect: $1,986 per each
- Electrical Service Wire, Furnish: $11.71 per linear foot
- Pole Cable Distribution System: $915.00 per each