Manhole, Adjust, Utilities: cost per each in Broward County, FL

The median awarded price is $1,000 per each, from 20 winning bids on 17 public projects in Broward County, FL (2024–2025). Half of the awarded prices fall between $850.00 and $1,143.

Cost by state › Florida › Broward County › Manhole, Adjust, Utilities

$1,000median per each
$850.00 – $1,143middle half (25th–75th percentile)
20winning bids, 17 source documents
2024–2025lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $500.00 in 2019 to $1,000 in 2024 (+100%).

YearMedian per eachWinning bids
2019$500.007
2021$567.797
2022$700.005
2024$1,00017

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Aug 27, 2025FDOT3 EA$1,000Open bid tab, T4728 ↗
Jan 29, 2025FDOT7 EA$1,000Open bid tab, T4705 ↗
Jan 29, 2025FDOT2 EA$1,491Open bid tab, T4713 ↗
Oct 30, 2024FDOT2 EA$1,250Open bid tab, T4695 ↗
Sep 25, 2024FDOT16 EA$1,107Open bid tab, T4681 ↗