Street Lighting · awarded bid prices · Broward County
Electrical Service Wire, Furnish: cost per linear foot in Broward County, FL
The median awarded price is $11.71 per linear foot, from 36 winning bids on 24 public projects in Broward County, FL (2024–2026). Half of the awarded prices fall between $8.25 and $15.40.
Cost by state › Florida › Broward County › Electrical Service Wire, Furnish
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $6.11 in 2020 to $12.43 in 2025 (+103%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2020 | $6.11 | 6 |
| 2021 | $7.00 | 10 |
| 2022 | $6.40 | 6 |
| 2023 | $11.30 | 6 |
| 2024 | $9.64 | 16 |
| 2025 | $12.43 | 17 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 8341 LF | $5.10 | Open bid tab, T4757 ↗ |
| Mar 25, 2026 | FDOT | 772 LF | $16.18 | Open bid tab, T4734 ↗ |
| Mar 25, 2026 | FDOT | 15 LF | $30.00 | Open bid tab, T4753 ↗ |
| Dec 3, 2025 | FDOT | 1153 LF | $11.00 | Open bid tab, T4717 ↗ |
| Sep 24, 2025 | FDOT | 13 LF | $16.10 | Open bid tab, T4741 ↗ |
The same item across Florida: statewide figures. See every awarded price for this item on the Electrical Service Wire, Furnish item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $24.23 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Light Pole Complete, F&I: $11,000 per each
- Lighting Conductors, F&I: $4.95 per linear foot
- Electrical Service Disconnect: $1,986 per each
- Pole Cable Distribution System: $915.00 per each