Street Lighting · awarded bid prices · Palm Beach County
Prestressed Concrete Pole, F&I: cost per each in Palm Beach County, FL
The median awarded price is $2,946 per each, from 24 winning bids on 16 public projects in Palm Beach County, FL (2023–2026). Half of the awarded prices fall between $2,285 and $3,739.
Cost by state › Florida › Palm Beach County › Prestressed Concrete Pole, F&I
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1,750 in 2021 to $3,091 in 2026 (+77%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2021 | $1,750 | 5 |
| 2023 | $3,209 | 8 |
| 2024 | $2,482 | 5 |
| 2025 | $2,605 | 10 |
| 2026 | $3,091 | 8 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 29, 2026 | FDOT | 1 EA | $2,932 | Open bid tab, T4747 ↗ |
| May 20, 2026 | FDOT | 2 EA | $3,052 | Open bid tab, T4666 ↗ |
| Mar 25, 2026 | FDOT | 8 EA | $3,112 | Open bid tab, T4735 ↗ |
| Mar 25, 2026 | FDOT | 6 EA | $3,070 | Open bid tab, T4740 ↗ |
| Aug 27, 2025 | FDOT | 1 EA | $2,347 | Open bid tab, T4702 ↗ |
The same item across Florida: statewide figures. See every awarded price for this item on the Prestressed Concrete Pole, F&I item page.
Related items in Palm Beach County
- Conduit, Furnish & Install: $44.39 per linear foot
- Conduit, Furnish & Install, Open: $21.30 per linear foot
- Pull & Splice Box, F&I, 13" x 24": $1,744 per each
- Lighting Conductors, F&I: $3.80 per linear foot
- Pull & Splice Box, F&I, 17" X 30": $1,674 per each
- Electrical Service Wire, Furnish: $11.15 per linear foot
- Pole Cable Distribution System: $1,052 per each
- Aluminum Signals Pole, Pedestal: $2,743 per each