ItemPerMedianMiddle halfWinning bids
Earth Excavationcubic yard$49.00$31.00 – $80.001,039
Raised Ref Pvt Mk Remeach$15.00$9.00 – $25.00959
Raised Refl Pavt Mkreach$49.65$40.11 – $90.00958
Protective Coatsquare yard$2.00$1.00 – $3.75955
Long Joint Sealantlinear foot$3.40$2.80 – $4.74908
Hma Surf Rem Butt Jtsquare yard$17.87$7.49 – $29.16844
Nitrogen Fert Nutrpound$3.00$2.00 – $5.00766
Potassium Fert Nutrpound$3.00$2.00 – $5.00765
Temp Info Signingsquare foot$20.00$15.51 – $28.64762
Sidewalk Remsquare foot$3.15$2.15 – $5.00739
Pavement Remsquare yard$20.00$14.00 – $35.00693
Thpl Pvt Mk Line 4linear foot$0.92$0.75 – $1.45692
Detectable Warningssquare foot$40.00$31.00 – $47.25673
Non Spl Waste Disposlcubic yard$92.17$70.87 – $125.00665
Thpl Pvt Mk Line 24linear foot$6.25$5.50 – $11.00663
Comb Curb Gutter Remlinear foot$12.23$8.52 – $20.96663
Soil Disposal Analyeach$1,450$1,200 – $1,650661
Thpl Pvt Mk Line 6linear foot$1.45$1.09 – $2.15656
Thpl Pvt Mk Line 12linear foot$3.32$2.70 – $6.16652
Perimeter Eros Barlinear foot$3.85$2.80 – $5.47648
Temp Eros Contr Seedpound$5.00$3.00 – $7.07618
Sign Panel T1square foot$34.00$27.50 – $48.08615
Reinf Bars, Epoxy Ctdpound$2.50$1.87 – $4.00606
Thpl Pvt Mk Ltr & Symsquare foot$6.00$5.25 – $9.00594
Temporary Rampsquare yard$20.58$10.02 – $37.11589
Phosphorus Fert Nutrpound$3.10$2.00 – $5.00581
Agg Wedge Shld Type Bton$52.39$38.77 – $84.77562
Drive Pavement Remsquare yard$20.00$15.00 – $30.00550
Mod Ureth Pm Line 4linear foot$1.42$0.8 – $3.50534
Temp Conc Barrierlinear foot$35.00$26.00 – $46.33533
Guardrail Removlinear foot$8.25$6.24 – $10.86530
Pc Conc Sidewalk 5square foot$11.00$9.36 – $15.00522
Tr Bar Trm T1 Spl Taneach$3,960$3,592 – $4,432503
Topsoil F & P 4square yard$7.00$5.12 – $12.18503
Terminal Marker - Daeach$50.00$42.00 – $53.92497
Trench Backfillcubic yard$60.00$42.88 – $84.25488
Rel Temp Conc Barrierlinear foot$9.00$5.17 – $13.06456
Incidental Hma Surfton$266.94$175.00 – $395.16454
Erosion Contr Blanketsquare yard$2.00$1.42 – $3.21448
Teles Stl Sin Supportlinear foot$20.00$17.06 – $28.00442
Filter Fabricsquare yard$5.00$3.41 – $7.00439
Temp Pvt Mk L4 T4 Tapelinear foot$1.30$0.962 – $1.50434
Conc Sup-Strcubic yard$2,200$1,550 – $3,500433
Spbgr Ty A 6Ft Postslinear foot$36.00$31.77 – $41.90420
Inlet Filterseach$200.00$155.50 – $257.12412
Seeding Cl 2Aacre$4,000$2,500 – $7,500407
Mod Ureth Pm Line 6linear foot$1.65$1.05 – $4.03407
Inlet & Pipe Protecteach$206.00$146.50 – $300.00403
Temp Ditch Checkslinear foot$14.00$10.00 – $20.00401
Grdrail Ref Type Aeach$12.00$10.49 – $16.00384
Furnished Excavationcubic yard$38.00$21.49 – $65.00376
Rem & Disp Uns Matlcubic yard$40.00$25.00 – $65.00375
Conc Structcubic yard$1,262$1,000 – $1,790374
Conc Remcubic yard$2,500$1,600 – $3,788374
Hma Sc Il-9.5 D N70ton$104.00$89.56 – $165.25364
Name Plateseach$937.66$750.00 – $1,200345
Saw Cutslinear foot$5.12$3.00 – $8.96340
Structure Excavationcubic yard$45.00$32.00 – $65.00322
Mowingacre$332.50$126.50 – $550.0096
Rock Excavationcubic yard$160.00$56.00 – $250.0031
Seedingacre$6,474$4,968 – $7,90629
Inlet Protectioneach$275.00$225.00 – $302.5025
Unclassified Excavationcubic yard$40.00$27.37 – $57.5019
Silt Fencelinear foot$7.00$5.00 – $12.0317
Mulchingacre$7,150$3,495 – $10,85215
Remove Bituminous Pavementsquare yard$15.00$11.00 – $22.4713
Pavement Marking Removalsquare foot$6.72$3.00 – $13.6912