| Mobilization | ls | 22 | — | $19,000 | $1,816 – $533,822 | Jul 23, 2026, Bid tabulation p. 1 |
| Sidewalk remove | square foot | 20 | $2.70 | $2.70 | $1.64 – $4.77 | Feb 10, 2025, Bid tabulation p. 1 |
| Traffic Control And Protection, (Special) | ls | 18 | — | $13,100 | $3,500 – $150,000 | Jul 23, 2026, Bid tabulation p. 1 |
| Earth Excavation | cubic yard | 17 | $55.83 | $92.43 | $23.00 – $176.65 | Apr 22, 2025, Bid tabulation p. 1 |
| Detectable Warnings | square foot | 16 | $30.50 | $38.09 | $22.93 – $40.00 | Apr 22, 2025, Bid tabulation p. 1 |
| Driveway pavement remove | square yard | 15 | $22.59 | $61.92 | $14.00 – $77.00 | Feb 10, 2025, Bid tabulation p. 1 |
| Construction Layout | ls | 14 | — | $25,601 | $2,248 – $175,540 | Apr 22, 2025, Bid tabulation p. 1 |
| Pavement remove | square yard | 14 | $22.93 | $17.95 | $15.00 – $66.99 | Feb 10, 2025, Bid tabulation p. 1 |
| Combination curb and gutter remove | linear foot | 13 | $14.00 | $22.11 | $8.00 – $78.84 | Feb 10, 2025, Bid tabulation p. 1 |
| Inlet Filters | each | 13 | $200.00 | $264.17 | $99.38 – $1,167 | Apr 22, 2025, Bid tabulation p. 1 |
| Portland cement concrete sidewalk, 4 inch | square foot | 12 | $11.05 | $13.04 | $6.45 – $27.71 | Feb 10, 2025, Bid tabulation p. 1 |
| Topsoil furnish and place, 4 inch | square yard | 11 | $10.47 | $11.68 | $5.00 – $13.43 | Feb 10, 2025, Bid tabulation p. 1 |
| Curb remove | linear foot | 10 | $13.25 | $25.26 | $10.61 – $113.89 | Mar 25, 2024, Bid tabulation p. 1 |
| Inlet to be adjusted | each | 10 | $821.05 | $842.10 | $601.94 – $2,393 | Feb 10, 2025, Bid tabulation p. 1 |
| Supplemental Watering | unit | 10 | $163.13 | $166.84 | $1.00 – $312.00 | Feb 10, 2025, Bid tabulation p. 1 |
| Potassium Fertilizer Nutrient | pound | 10 | $7.79 | $3.06 | $3.00 – $11.27 | Feb 10, 2025, Bid tabulation p. 1 |
| Nitrogen Fertilizer Nutrient | pound | 10 | $7.79 | $3.06 | $3.00 – $11.27 | Feb 10, 2025, Bid tabulation p. 1 |
| Combination Concrete Curb And Gutter, Type B-6.12 | linear foot | 10 | $62.44 | $63.25 | $30.00 – $107.07 | Jul 23, 2026, Bid tabulation p. 1 |
| Sodding | square yard | 10 | $20.69 | $37.87 | $16.83 – $65.04 | Apr 22, 2025, Bid tabulation p. 1 |
| Portland Cement Concrete Driveway Pavement, 6 Inch | square yard | 9 | $87.58 | $102.15 | $63.00 – $148.50 | Feb 10, 2025, Bid tabulation p. 1 |
| Phosphorus Fertilizer Nutrient | pound | 9 | $7.60 | $3.06 | $3.00 – $11.27 | Feb 10, 2025, Bid tabulation p. 1 |
| Concrete Curb, Type B | linear foot | 9 | $55.00 | $109.27 | $32.81 – $155.63 | Feb 22, 2024, Bid tabulation p. 1 |
| Portland Cement Concrete Driveway Pavement, 8 Inch | square yard | 8 | $88.00 | $148.34 | $68.00 – $148.34 | Mar 25, 2024, Bid tabulation p. 1 |
| Trench Backfill | cubic yard | 7 | $43.69 | $56.40 | $33.24 – $58.99 | Apr 22, 2025, Bid tabulation p. 1 |
| Asphalt materials (tack coat) | pound | 6 | $1.89 | $1.69 | $1.69 – $2.63 | Feb 22, 2024, Bid tabulation p. 1 |
| Storm sewers, type 1, water main quality pipe, 12 inch | linear foot | 6 | $112.99 | $109.87 | $109.87 – $130.36 | Feb 10, 2025, Bid tabulation p. 2 |
| Combination Concrete Curb And Gutter, Type B-6.18 | linear foot | 6 | $46.81 | $78.48 | $32.76 – $78.48 | Feb 10, 2025, Bid tabulation p. 1 |
| Sodding Salt Tolerant | square yard | 6 | $15.85 | $16.74 | $11.00 – $94.30 | Jan 10, 2023, Bid tabulation p. 1 |
| Hot-Mix Asphalt Surface Course, Il-9.5, Mix "C", N50 | ton | 5 | $154.50 | $131.44 | $114.17 – $165.44 | Mar 25, 2024, Bid tabulation p. 1 |
| Aggregate For Temporary Access | ton | 5 | $46.33 | $48.27 | $27.32 – $50.00 | Mar 25, 2024, Bid tabulation p. 1 |
| Inlet, type g-1 | each | 5 | $3,973 | $4,981 | $2,200 – $4,981 | Feb 10, 2025, Bid tabulation p. 2 |
| Hot-mix asphalt surface remove, variable deep | square yard | 5 | $16.68 | $16.68 | $5.35 – $37.75 | Feb 10, 2025, Bid tabulation p. 1 |
| Pavement patch (special) | square yard | 5 | $140.50 | $244.20 | $133.89 – $244.20 | Mar 23, 2023, Bid tabulation p. 1 |
| Manhole to be adjusted | each | 5 | $1,210 | $1,274 | $545.07 – $2,000 | Feb 10, 2025, Bid tabulation p. 1 |
| Protective Coat | square yard | 5 | — | $0.01 | $0.01 – $2.00 | Jan 10, 2023, Bid tabulation p. 1 |
| Bit Matls Tack Ct | pound | 5 | $1.10 | $2.13 | $1.00 – $2.13 | Apr 22, 2025, Bid tabulation p. 1 |
| P.c.c. sidewalk, 4 inch | square foot | 5 | $13.70 | $23.60 | $6.75 – $23.60 | Sep 13, 2022, Bid tabulation p. 1 |
| Remove And Reset Brick Sidewalk | square foot | 4 | — | $20.00 | $10.00 – $150.00 | Sep 21, 2021, Bid tabulation p. 1 |
| P.c.c. driveway pavement, 8 inch | square yard | 4 | — | $110.00 | $80.00 – $110.00 | Sep 21, 2021, Bid tabulation p. 1 |
| P.c.c. driveway pavement, 6 inch | square yard | 4 | — | $92.00 | $70.00 – $92.00 | Sep 21, 2021, Bid tabulation p. 1 |