| Glass Beads | pound | 8 | $0.475 | $0.44 | $0.33 – $5.00 | Mar 26, 2026, Bid tabulation p. 1 |
| Aggregate surface course, ca-6, type b | ton | 8 | $13.73 | $6.50 | $6.50 – $17.00 | May 6, 2026, Bid tabulation p. 1 |
| Aggregate Surface Course, CA-6, Type B | ton | 7 | $13.34 | $13.34 | $10.05 – $17.90 | Mar 1, 2023, Bid tabulation p. 1 |
| Pipe culvert, type 1, 15 inch | linear foot | 6 | $18.96 | $18.96 | $18.96 | Mar 1, 2023, Bid tabulation p. 1 |
| Bit material (seal coat) | ton | 6 | $756.00 | $730.00 | $720.00 – $905.00 | Mar 26, 2026, Bid tabulation p. 1 |
| Aggregate (seal Coat) | ton | 6 | $38.50 | $39.00 | $30.00 – $57.00 | Mar 26, 2026, Bid tabulation p. 1 |
| Hot mix asphalt sc, il-9.5, mix c, n50 | ton | 4 | — | $120.29 | $75.75 – $120.29 | Apr 5, 2023, Bid tabulation p. 1 |
| Hot mix asphalt sc, il-9.5, c, n50 s | ton | 4 | — | $80.00 | $78.75 – $91.00 | Mar 26, 2026, Bid tabulation p. 1 |
| Bit material (tack coat) | pound | 4 | — | $1.00 | $0.01 – $1.00 | Mar 26, 2026, Bid tabulation p. 1 |
| Hot mix asphalt surface remove butt joint | square yard | 4 | — | $12.50 | $7.50 – $12.50 | Mar 26, 2026, Bid tabulation p. 1 |
| Bit Materials (Tack Coat) | pound | 3 | — | $0.01 | $0.01 – $0.5 | Apr 5, 2023, Bid tabulation p. 1 |
| Hot mix asphalt surface remvl (butt joint) | square yard | 3 | — | $22.00 | $10.00 – $22.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Yellow Latex Traffic Paint | gallon | 3 | — | $20.25 | $20.25 – $250.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Pipe culvert, type 1, 18 inch | linear foot | 3 | — | $33.26 | $27.90 – $33.26 | Mar 6, 2025, Bid tabulation p. 1 |
| Aggregate shoulder, type b | ton | 3 | — | $36.00 | $35.00 – $56.50 | Mar 26, 2026, Bid tabulation p. 1 |
| Paint pavement marking line, 4 inch | linear foot | 3 | — | $0.55 | $0.25 – $0.55 | Mar 26, 2026, Bid tabulation p. 1 |
| Rejuvenator-Reclamite | square yard | 3 | — | $1.27 | $1.12 – $1.27 | Mar 26, 2026, Bid tabulation p. 1 |
| Bit material (fog coat) | square yard | 3 | — | $0.55 | $0.52 – $0.61 | Mar 26, 2026, Bid tabulation p. 1 |
| Traffic Control Complete | ls | 3 | — | $1,500 | $1,500 – $15,900 | Sep 24, 2026, Bid tabulation p. 1 |
| Bit Matls (Tack Coat) | pound | 3 | — | $0.01 | $0.01 – $1.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Pc, type 1, 15 inch connecting band | each | 2 | — | $37.92 | $37.92 | Mar 1, 2023, Bid tabulation p. 1 |
| Pipe culvert, type 1, 30 inch | linear foot | 2 | — | $46.50 | $46.50 | Mar 1, 2023, Bid tabulation p. 1 |
| Hot mix asphalt surface remove (butt | square yard | 2 | — | $11.26 | $11.26 – $17.00 | Apr 5, 2023, Bid tabulation p. 1 |
| Hot mix asphalt sc,il 9.5,mix c,n50sp | ton | 2 | — | $130.00 | $81.00 – $130.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Paint pvt marking, line 4 inch | linear foot | 2 | — | $0.25 | $0.25 – $4.40 | Mar 31, 2025, Bid tabulation p. 1 |
| White Latex Traffic Paint | gallon | 2 | — | $20.25 | $20.25 – $22.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Aggregate (Prime Coat) | ton | 2 | — | $1.00 | $1.00 | Mar 31, 2025, Bid tabulation p. 1 |
| Bit material (prime coat | ton | 2 | — | $1,246 | $1,246 – $1,390 | Mar 31, 2025, Bid tabulation p. 1 |
| Preparation of base | square yard | 2 | — | $0.85 | $0.85 – $1.10 | Mar 31, 2025, Bid tabulation p. 1 |
| Pipe culvert, type 1, 36 inch | linear foot | 2 | — | $68.54 | $55.80 – $68.54 | Mar 6, 2025, Bid tabulation p. 1 |
| pre-wet tank system as specified | each | 2 | — | $188,326 | $168,315 – $188,326 | Jan 29, 2026, Bid tabulation p. 1 |
| Hot mix asphalt sc, il-9.5, c, n50, sp | ton | 2 | — | $138.85 | $101.00 – $138.85 | Mar 26, 2026, Bid tabulation p. 1 |
| Aggregate (CA-16) | ton | 2 | — | $31.85 | $31.05 – $31.85 | Mar 26, 2026, Bid tabulation p. 1 |
| Asphalt materials course-2 furnish & | gallon | 2 | — | $9.49 | $9.30 – $9.49 | Mar 26, 2026, Bid tabulation p. 1 |
| Aggregate shoulder, type b | ton | 2 | — | $73.83 | $38.00 – $73.83 | Mar 26, 2026, Bid tabulation p. 1 |
| Manhole adjust | each | 2 | — | $300.00 | $300.00 – $950.00 | Mar 26, 2026, Bid tabulation p. 1 |
| One Ton w/11's stainless | each | 1 | — | $53,110 | $53,110 | Oct 29, 2026, Bid tabulation p. 1 |
| Whilte Latex Traffic Marking Paint | gallon | 1 | — | $21.86 | $21.86 | Apr 6, 2022, Bid tabulation p. 1 |
| Yellow Latex Traffic Marking Paint | gallon | 1 | — | $21.86 | $21.86 | Apr 6, 2022, Bid tabulation p. 1 |
| Pipe culvert, type 1, 36 inch connecting band | each | 1 | — | $111.60 | $111.60 | Mar 1, 2023, Bid tabulation p. 1 |