Construction unit costs in Peoria County, IL

Median awarded unit prices for 35 items on public projects in Peoria County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Illinois › Peoria County

ItemPerMedianMiddle halfWinning bidsLatest source document
Modified ureth pm line 4linear foot$1.02$0.83 – $1.8426Jul 31, 2026, Open bid tab, 68L02 ↗
P Bit Matls Tack Ctpound$1.70$0.998 – $2.3724Jul 31, 2026, Open bid tab, 68L01 ↗
Shrt trm pavement mk removesquare foot$2.80$2.00 – $6.5223Jul 31, 2026, Open bid tab, 68L01 ↗
Detectable Warningssquare foot$30.30$25.38 – $33.4422Jun 12, 2026, Open bid tab, 68J56 ↗
Filter Fabricsquare yard$4.63$3.50 – $6.0022Feb 27, 2026, Open bid tab, 68J51 ↗
Earth Excavationcubic yard$54.19$39.56 – $67.8922Jun 12, 2026, Open bid tab, 68J56 ↗
Protective Coatsquare yard$3.15$1.53 – $4.0622Feb 27, 2026, Open bid tab, 68J57 ↗
Short terminal pavement mkinglinear foot$2.49$1.94 – $3.8920Jul 31, 2026, Open bid tab, 68L01 ↗
Hot mix asphalt surface remove butt jointsquare yard$31.25$15.10 – $48.2520Jul 31, 2026, Open bid tab, 68L01 ↗
Modified ureth pm line 24linear foot$8.59$5.88 – $12.0720Jul 31, 2026, Open bid tab, 68L01 ↗
Raised reflective pavement mkreach$53.00$42.12 – $95.0019Jul 31, 2026, Open bid tab, 68L01 ↗
Modified ureth pm line 6linear foot$1.38$1.19 – $2.0519Jul 31, 2026, Open bid tab, 68L02 ↗
Grv rcsd pvt marking 5linear foot$0.69$0.445 – $1.0418Jun 12, 2026, Open bid tab, 68J56 ↗
Modified ureth pm line 12linear foot$3.70$2.73 – $5.1718Jul 31, 2026, Open bid tab, 68L01 ↗
Material transfer deviceton$4.71$2.13 – $7.9217Jul 31, 2026, Open bid tab, 68L01 ↗
Temporary Rampsquare yard$36.97$21.08 – $55.0117Jul 31, 2026, Open bid tab, 68L01 ↗
Modified ureth pm ltr-symbolsquare foot$6.16$4.95 – $9.0017Jul 31, 2026, Open bid tab, 68L01 ↗
Modified ureth pm line 8linear foot$1.98$1.71 – $2.7217Jun 12, 2026, Open bid tab, 68J56 ↗
Nitrogen Fert Nutrpound$4.50$2.00 – $6.4816Jun 12, 2026, Open bid tab, 68J56 ↗
Phosphorus Fert Nutrpound$4.50$2.00 – $6.4816Jun 12, 2026, Open bid tab, 68J56 ↗
Potassium Fert Nutrpound$4.50$2.00 – $6.4816Jun 12, 2026, Open bid tab, 68J56 ↗
Perimeter erosion barlinear foot$4.92$4.00 – $5.4916Feb 27, 2026, Open bid tab, 68474 ↗
Tr Bar Trm T1 Spl Taneach$3,875$3,400 – $4,12816Jun 12, 2026, Open bid tab, 68C93 ↗
Guardrail removelinear foot$6.38$5.60 – $8.6216Jun 12, 2026, Open bid tab, 68C93 ↗
Terminal Marker - Daeach$50.00$50.00 – $51.1216Jun 12, 2026, Open bid tab, 68C93 ↗
Raised ref pvt mk removeeach$25.27$13.86 – $36.3916Jul 31, 2026, Open bid tab, 68L01 ↗
Grv rcsd pvt marking 7linear foot$0.67$0.55 – $1.4816Jun 12, 2026, Open bid tab, 68C93 ↗
Temporary erosion control seedpound$6.00$4.50 – $13.5015Feb 27, 2026, Open bid tab, 68474 ↗
Grv rcsd pvt marking 9linear foot$1.32$0.9 – $1.5415Jun 12, 2026, Open bid tab, 68C93 ↗
Grv rcsd pvt marking 25linear foot$5.11$4.70 – $6.7015Jun 12, 2026, Open bid tab, 68J56 ↗
Guardrail aggregate erosion controlton$95.00$86.00 – $122.5015Jun 12, 2026, Open bid tab, 68C93 ↗
Pavement removesquare yard$19.76$13.13 – $36.0014Feb 27, 2026, Open bid tab, 68J46 ↗
Grv rcsd pvt marking 13linear foot$2.62$2.33 – $3.7214Jun 12, 2026, Open bid tab, 68J56 ↗
Topsoil F & P 4square yard$11.00$7.50 – $14.7113Feb 27, 2026, Open bid tab, 68474 ↗
Combination curb gutter removelinear foot$12.01$5.75 – $20.1212Jun 12, 2026, Open bid tab, 68J56 ↗