Construction unit costs in Madison County, IL

Median awarded unit prices for 59 items on public projects in Madison County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Illinois › Madison County

ItemPerMedianMiddle halfWinning bidsLatest source document
Bit Matls Tack Ctpound$2.25$1.50 – $3.0252Jun 12, 2026, Open bid tab, 76R32 ↗
Raised reflective pavement mkreach$60.00$46.33 – $102.3543Jul 31, 2026, Open bid tab, 76V11 ↗
Earth Excavationcubic yard$48.12$26.88 – $66.7540Jun 12, 2026, Open bid tab, 76R32 ↗
Short terminal pavement mkinglinear foot$2.50$1.32 – $3.3239Jul 31, 2026, Open bid tab, 76V11 ↗
Sign Panel T1square foot$34.15$28.76 – $50.0038Jun 12, 2026, Open bid tab, 76R32 ↗
Nitrogen Fert Nutrpound$5.75$3.00 – $10.0037Jun 12, 2026, Open bid tab, 76R32 ↗
Phosphorus Fert Nutrpound$5.75$3.00 – $10.0037Jun 12, 2026, Open bid tab, 76R32 ↗
Potassium Fert Nutrpound$5.75$3.00 – $10.0037Jun 12, 2026, Open bid tab, 76R32 ↗
Pavement removesquare yard$17.00$12.25 – $35.0037Jun 12, 2026, Open bid tab, 76R32 ↗
Combination curb gutter removelinear foot$16.00$11.50 – $23.3133Jun 12, 2026, Open bid tab, 76R32 ↗
Detectable Warningssquare foot$49.36$34.75 – $63.2732Jun 12, 2026, Open bid tab, 97884 ↗
Drive pavement removesquare yard$24.27$17.38 – $32.5632Jun 12, 2026, Open bid tab, 97884 ↗
Long joint seallinear foot$4.46$3.65 – $6.6232Jun 12, 2026, Open bid tab, 76V17 ↗
Inlet & Pipe Protecteach$175.00$93.28 – $277.5031Jun 12, 2026, Open bid tab, 76R32 ↗
Combination cc&g type b-6.24linear foot$68.50$42.55 – $88.7530Feb 27, 2026, Open bid tab, 97882 ↗
Sidewalk removesquare foot$3.20$2.04 – $5.0030Jun 12, 2026, Open bid tab, 76U38 ↗
Mulching method 2acre$5,436$3,564 – $7,06830Jun 12, 2026, Open bid tab, 76R32 ↗
Teles steel sin supportlinear foot$19.00$16.25 – $25.2029Jun 12, 2026, Open bid tab, 76R32 ↗
Pc concrete sidewalk 4square foot$13.65$9.00 – $20.0029Jun 12, 2026, Open bid tab, 97896 ↗
Trench Backfillcubic yard$60.00$52.99 – $72.0028Apr 24, 2026, Open bid tab, 97840 ↗
Temporary erosion control seedpound$6.00$4.75 – $8.0628Feb 27, 2026, Open bid tab, 97882 ↗
Thpl pvt mk ltr & symbolsquare foot$12.60$10.80 – $15.0025Jun 12, 2026, Open bid tab, 76R32 ↗
Thpl Pvt Mk Line 12linear foot$9.50$8.15 – $10.0025Jun 12, 2026, Open bid tab, 97884 ↗
Thpl Pvt Mk Line 24linear foot$15.00$12.27 – $19.0025Jun 12, 2026, Open bid tab, 97884 ↗
Pcc driveway pavement 6square yard$140.00$118.00 – $156.7025Jun 12, 2026, Open bid tab, 97884 ↗
Thpl Pvt Mk Line 6linear foot$1.83$0.835 – $3.3324Jun 12, 2026, Open bid tab, 76R32 ↗
Non Spl Waste Disposlcubic yard$106.75$58.15 – $171.9724Jun 12, 2026, Open bid tab, 76U38 ↗
Soil Disposal Analyeach$1,439$1,394 – $1,61224Jun 12, 2026, Open bid tab, 76U38 ↗
Aggregate-temporary accesston$44.50$35.94 – $54.8824Jun 12, 2026, Open bid tab, 97896 ↗
Dowel Bars 1 1/2each$30.00$25.00 – $37.2524Jul 31, 2026, Open bid tab, 76V11 ↗
Remove inleteach$600.00$465.00 – $982.5023Apr 24, 2026, Open bid tab, 97840 ↗
Grdrail Ref Type Aeach$10.50$10.06 – $10.9622Jun 12, 2026, Open bid tab, 76R32 ↗
Material transfer deviceton$5.61$5.00 – $6.5622Jun 12, 2026, Open bid tab, 76V17 ↗
Terminal Marker - Daeach$42.00$26.00 – $46.0021Jun 12, 2026, Open bid tab, 76R32 ↗
Concrete curb tblinear foot$67.00$54.00 – $85.0021Apr 24, 2026, Open bid tab, 97840 ↗
Bit Matls Pr Ctpound$1.85$1.00 – $3.4021Feb 27, 2026, Open bid tab, 97882 ↗
Hot mix asphalt shoulderton$140.57$124.71 – $155.8021Jun 12, 2026, Open bid tab, 76V17 ↗
Perimeter erosion barlinear foot$4.62$3.46 – $6.0020Jun 12, 2026, Open bid tab, 76R32 ↗
Tr Bar Trm T1 Spl Taneach$3,350$3,135 – $3,68820Jun 12, 2026, Open bid tab, 76R32 ↗
Guardrail removelinear foot$6.80$5.21 – $7.4120Jun 12, 2026, Open bid tab, 76R32 ↗
Thpl Pvt Mk Line 4linear foot$1.26$1.00 – $1.7720Jun 12, 2026, Open bid tab, 97884 ↗
Incidental hot mix asphalt surfaceton$320.24$293.28 – $427.7120Apr 24, 2026, Open bid tab, 97840 ↗
Saw Cutslinear foot$8.00$5.00 – $9.0020Jul 31, 2026, Open bid tab, 76V11 ↗
Filter Fabricsquare yard$5.24$4.58 – $7.6519Jun 12, 2026, Open bid tab, 76V17 ↗
Storm sew class a 1 12linear foot$100.00$64.20 – $127.2519Apr 24, 2026, Open bid tab, 97840 ↗
Temporary pvt mk line 4 - paintlinear foot$0.01$0.01 – $0.0119Apr 24, 2026, Open bid tab, 97840 ↗
Hot mix asphalt sc il-9.5 d n70ton$166.00$160.00 – $175.0017Jun 12, 2026, Open bid tab, 97884 ↗
Spbgr type a 6ft postlinear foot$31.50$27.00 – $34.9017Jun 12, 2026, Open bid tab, 76R32 ↗
Pcc driveway pavement 8square yard$147.00$142.00 – $158.0017Jun 12, 2026, Open bid tab, 97884 ↗
Traffic bar terminal t6each$4,050$3,698 – $4,72517Jun 12, 2026, Open bid tab, 76R32 ↗
Reinforced bars, epoxy ctdpound$2.28$1.75 – $3.8116Jun 12, 2026, Open bid tab, 76R32 ↗
Storm sew class a 1 15linear foot$84.00$68.00 – $108.2015Apr 24, 2026, Open bid tab, 97840 ↗
Temporary ditch checkslinear foot$22.00$14.70 – $23.8915Jan 16, 2026, Open bid tab, 76A46 ↗
Concrete median surface 4square foot$24.00$14.30 – $30.0015Apr 24, 2026, Open bid tab, 97840 ↗
Welded wire reinforcedsquare yard$19.80$11.30 – $21.0015Jul 31, 2026, Open bid tab, 76V11 ↗
Curb, removelinear foot$17.95$12.00 – $22.2014Apr 24, 2026, Open bid tab, 97840 ↗
Concrete fdn type alinear foot$495.20$349.25 – $680.0014Jun 12, 2026, Open bid tab, 76U38 ↗
Elcbl C Signal 14 2Clinear foot$2.54$2.00 – $4.3514Jun 12, 2026, Open bid tab, 76U38 ↗
Tie Bars 3/4each$22.00$20.00 – $30.0013Jul 31, 2026, Open bid tab, 76V11 ↗