Construction unit costs in Kane County, IL

Median awarded unit prices for 77 items on public projects in Kane County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Illinois › Kane County

ItemPerMedianMiddle halfWinning bidsLatest source document
Bit Matls Tack Ctpound$0.01$0.01 – $0.0158Sep 18, 2026, Open bid tab, 62X33 ↗
Temporary info signingsquare foot$16.50$15.00 – $20.0056Sep 18, 2026, Open bid tab, 62X33 ↗
Thpl Pvt Mk Line 4linear foot$0.85$0.75 – $1.0149Sep 18, 2026, Open bid tab, 62X33 ↗
Thpl Pvt Mk Line 12linear foot$3.00$2.50 – $3.5049Sep 18, 2026, Open bid tab, 62X33 ↗
Thpl Pvt Mk Line 24linear foot$6.00$5.28 – $6.7747Sep 18, 2026, Open bid tab, 62X33 ↗
Hot mix asphalt surface remove butt jointsquare yard$20.00$12.00 – $25.0047Sep 18, 2026, Open bid tab, 62X33 ↗
Thpl Pvt Mk Line 6linear foot$1.36$1.06 – $1.5646Sep 18, 2026, Open bid tab, 62X33 ↗
Long joint seallinear foot$3.48$3.00 – $3.9746Sep 18, 2026, Open bid tab, 62X33 ↗
Thpl pvt mk ltr & symbolsquare foot$5.60$5.00 – $6.0044Sep 18, 2026, Open bid tab, 62X33 ↗
Sidewalk removesquare foot$2.83$2.00 – $4.6642Sep 18, 2026, Open bid tab, 61M10 ↗
Detectable Warningssquare foot$41.90$35.44 – $45.0040Sep 18, 2026, Open bid tab, 61M10 ↗
Pc concrete sidewalk 5square foot$11.00$10.00 – $14.5040Sep 18, 2026, Open bid tab, 61M10 ↗
Mix cr joint flangewyston$216.98$150.00 – $328.5039Sep 18, 2026, Open bid tab, 62X33 ↗
Topsoil F & P 4square yard$6.60$4.56 – $10.0039Sep 18, 2026, Open bid tab, 61M10 ↗
Earth Excavationcubic yard$40.97$34.44 – $50.0036Sep 18, 2026, Open bid tab, 61M10 ↗
Sodding Salt Tolerantsquare yard$29.75$17.69 – $68.0636Sep 18, 2026, Open bid tab, 61M10 ↗
Nitrogen Fert Nutrpound$3.00$2.00 – $3.1734Sep 18, 2026, Open bid tab, 61M10 ↗
Potassium Fert Nutrpound$3.00$2.00 – $3.1734Sep 18, 2026, Open bid tab, 61M10 ↗
Inlet Filterseach$200.00$152.50 – $218.7534Sep 18, 2026, Open bid tab, 61M10 ↗
Hot mix asphalt sc il-9.5 d n50ton$93.00$83.50 – $130.0033Sep 18, 2026, Open bid tab, 61M10 ↗
Non Spl Waste Disposlcubic yard$91.59$80.00 – $100.0032Sep 18, 2026, Open bid tab, 61M10 ↗
Soil Disposal Analyeach$1,300$968.12 – $1,60732Sep 18, 2026, Open bid tab, 61M10 ↗
Combination curb gutter removelinear foot$10.00$7.36 – $13.8030Sep 18, 2026, Open bid tab, 61M10 ↗
Sign Panel T1square foot$27.75$25.00 – $30.0030Sep 18, 2026, Open bid tab, 61M10 ↗
Raised ref pvt mk removeeach$15.00$9.25 – $20.2730Sep 18, 2026, Open bid tab, 62X33 ↗
Remove & disp uns materialcubic yard$40.00$30.00 – $47.5029Sep 18, 2026, Open bid tab, 61M10 ↗
Perimeter erosion barlinear foot$3.00$2.60 – $4.0028Sep 18, 2026, Open bid tab, 61M10 ↗
Pavement removesquare yard$19.00$10.00 – $24.0027Jul 31, 2026, Open bid tab, 61M13 ↗
Raised reflective pavement mkreach$46.30$37.75 – $61.1927Sep 18, 2026, Open bid tab, 62X33 ↗
Bit Matls Pr Ctpound$0.01$0.01 – $0.0127Sep 18, 2026, Open bid tab, 61M10 ↗
Temporary erosion control seedpound$3.15$2.00 – $5.0026Sep 18, 2026, Open bid tab, 61M10 ↗
Geotech fabric f/gr stabilizedsquare yard$2.81$2.00 – $3.5026Jul 31, 2026, Open bid tab, 61M13 ↗
Cc&g rmvl replace > 10ftlinear foot$62.00$53.50 – $80.0025Jul 31, 2026, Open bid tab, 61K67 ↗
Hot mix asphalt sc il-9.5 d n70ton$95.00$85.00 – $105.0025Sep 18, 2026, Open bid tab, 62X33 ↗
Main ex tr signal instaleach$3,080$1,500 – $5,25025Sep 18, 2026, Open bid tab, 61M10 ↗
Aggregate subgrade improvecubic yard$50.00$39.71 – $58.0025Jul 31, 2026, Open bid tab, 61M13 ↗
Drive pavement removesquare yard$16.00$13.00 – $18.7725Sep 18, 2026, Open bid tab, 61M10 ↗
Cc&g rmvl replace < = 10linear foot$73.50$61.12 – $100.0024Jul 31, 2026, Open bid tab, 61K67 ↗
Aggregate subgrade impr 12square yard$19.00$15.65 – $28.0124Jul 31, 2026, Open bid tab, 61M13 ↗
P hot mix asphalt bc il-4.75 n50ton$114.00$105.00 – $131.0523Jul 31, 2026, Open bid tab, 61K67 ↗
Combination cc&g tb6.12linear foot$40.00$30.91 – $52.3123Sep 18, 2026, Open bid tab, 61M10 ↗
Teles steel sin supportlinear foot$18.00$16.50 – $20.0023Sep 18, 2026, Open bid tab, 61M10 ↗
Fr & Lids Adjust Spleach$1,250$1,100 – $1,35023Sep 18, 2026, Open bid tab, 61M10 ↗
Tree Root Pruningeach$118.88$100.00 – $191.2522Sep 18, 2026, Open bid tab, 61M10 ↗
Sanitary manhole adjusteach$1,400$1,200 – $1,55022Jul 31, 2026, Open bid tab, 61K67 ↗
Trench Backfillcubic yard$48.00$25.00 – $53.1421Jul 31, 2026, Open bid tab, 61M13 ↗
Inlet adjusteach$582.50$492.50 – $762.5020Jul 31, 2026, Open bid tab, 61K67 ↗
Relocate sin pan assy taeach$150.00$125.00 – $250.0020Feb 27, 2026, Open bid tab, 61L39 ↗
Det loop replacelinear foot$20.56$16.85 – $35.1120Sep 18, 2026, Open bid tab, 62X33 ↗
Accessible pedestrian signaleach$2,300$2,000 – $2,64519Sep 18, 2026, Open bid tab, 61M10 ↗
Seeding class 2aacre$3,182$2,500 – $4,75019Jul 31, 2026, Open bid tab, 61M13 ↗
Elcbl C Egrdc 6 1Clinear foot$2.99$2.37 – $3.8519Sep 18, 2026, Open bid tab, 61M10 ↗
Erosion control blanketsquare yard$1.33$0.962 – $2.0018Jun 12, 2026, Open bid tab, 61M42 ↗
Undrgrd C Galvs 2linear foot$41.18$28.47 – $54.3018Sep 18, 2026, Open bid tab, 61M10 ↗
Drill Ex Handholeeach$694.44$521.75 – $847.5018Sep 18, 2026, Open bid tab, 61M10 ↗
Tree Trunk Protectioneach$117.03$100.00 – $275.0018Sep 18, 2026, Open bid tab, 61M10 ↗
Elcbl C Signal 14 2Clinear foot$2.26$1.70 – $3.1518Sep 18, 2026, Open bid tab, 61M10 ↗
Aggregate wedge shoulder type bton$59.78$50.00 – $70.1518Sep 18, 2026, Open bid tab, 62X33 ↗
Phosphorus Fert Nutrpound$3.00$2.96 – $3.3816Jun 12, 2026, Open bid tab, 61M42 ↗
Concrete fdn type a 12dlinear foot$416.18$342.50 – $458.3416Sep 18, 2026, Open bid tab, 61M10 ↗
Remove sin pan assy taeach$78.75$50.00 – $120.6216Apr 24, 2026, Open bid tab, 61L48 ↗
Undrgrd C Galvs 4linear foot$81.00$74.19 – $93.0716Sep 18, 2026, Open bid tab, 61M10 ↗
Elcbl C Signal 14 3Clinear foot$2.34$1.98 – $2.9316Sep 18, 2026, Open bid tab, 61M10 ↗
Man Adjusteach$750.00$612.50 – $809.6916Apr 24, 2026, Open bid tab, 61M17 ↗
Temporary tr signal timingeach$630.00$514.53 – $1,43515Sep 18, 2026, Open bid tab, 61M10 ↗
Topsoil excavation & placcubic yard$27.12$21.34 – $33.7515Sep 18, 2026, Open bid tab, 61M10 ↗
Remove elcbl fr conlinear foot$0.7$0.65 – $1.1915Sep 18, 2026, Open bid tab, 61M10 ↗
Elcbl C Lead 14 1Prlinear foot$1.88$1.61 – $3.4015Sep 18, 2026, Open bid tab, 61M10 ↗
Aggregate base course b 4square yard$7.25$5.78 – $10.0015Jul 31, 2026, Open bid tab, 61M13 ↗
Thpl Pvt Mk Line 8linear foot$1.87$1.60 – $2.0015Jun 12, 2026, Open bid tab, 61L30 ↗
Pedestrian sh led 1f bm cdteach$700.00$665.89 – $862.5015Sep 18, 2026, Open bid tab, 61M10 ↗
Temporary erosion control blanksquare yard$0.9$0.51 – $1.1314Apr 24, 2026, Open bid tab, 61L48 ↗
Storm sewer remove 12linear foot$19.35$16.34 – $27.7514Jul 31, 2026, Open bid tab, 61M13 ↗
Pipe underdrain t 2 4linear foot$23.00$16.50 – $28.7514Jul 31, 2026, Open bid tab, 61M13 ↗
Guardrail removelinear foot$10.60$8.00 – $33.2013Jul 31, 2026, Open bid tab, 61M13 ↗
Modified ureth pm line 4linear foot$1.25$0.85 – $2.2013Jul 31, 2026, Open bid tab, 61M13 ↗
Temporary ditch checkslinear foot$8.00$5.65 – $8.7612Jul 31, 2026, Open bid tab, 61M13 ↗