Temporary Ramp: cost per square yard in Peoria County, IL
The median awarded price is $36.97 per square yard, from 17 winning bids on 17 public projects in Peoria County, IL (2024–2026). Half of the awarded prices fall between $21.08 and $55.01.
Cost by state › Illinois › Peoria County › Temporary Ramp
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $15.26 in 2019 to $29.33 in 2026 (+92%).
| Year | Median per square yard | Winning bids |
|---|---|---|
| 2019 | $15.26 | 6 |
| 2020 | $14.68 | 8 |
| 2021 | $15.00 | 5 |
| 2024 | $62.48 | 5 |
| 2026 | $29.33 | 9 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 31, 2026 | IDOT | 73 SQ YD | $36.97 | Open bid tab, 68L01 ↗ |
| Jun 12, 2026 | IDOT | 1344.4 SQ YD | $15.00 | Open bid tab, 68C93 ↗ |
| Jun 12, 2026 | IDOT | 557 SQ YD | $54.79 | Open bid tab, 68J56 ↗ |
| Apr 24, 2026 | IDOT | 445 SQ YD | $15.00 | Open bid tab, 68J88 ↗ |
| Apr 24, 2026 | IDOT | 289 SQ YD | $29.33 | Open bid tab, 68J89 ↗ |
The same item across Illinois: statewide figures. See every awarded price for this item on the Temporary Ramp item page.
Related items in Peoria County
- Mod Ureth Pm Line 4: $1.02 per linear foot
- P Bit Matls Tack Ct: $1.70 per pound
- Shrt Trm Pavt Mk Rem: $2.80 per square foot
- Filter Fabric: $4.63 per square yard
- Protective Coat: $3.15 per square yard
- Short Term Pavt Mking: $2.49 per linear foot
- Mod Ureth Pm Line 24: $8.59 per linear foot
- Raised Refl Pavt Mkr: $53.00 per each