Median awarded unit prices for 67 items on public projects in Dallas County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Texas › Dallas County

ItemPerMedianMiddle halfWinning bidsLatest source document
Biodegradable erosion control logs (remove)linear foot$1.25$1.00 – $2.5859Oct 7, 2026, line 28 ↗
Reflective pavement marker type ii-c-reach$5.18$4.25 – $7.1344Oct 14, 2026, line 15 ↗
Portable Changeable Message Signday$100.00$65.41 – $150.3343Oct 14, 2026, line 7 ↗
Biodegradable erosion control logs (install) (18 inch)linear foot$6.25$4.25 – $10.0033Oct 7, 2026, line 10 ↗
Electrical conductor (no.6) barelinear foot$2.88$2.00 – $3.2632Oct 7, 2026, line 39 ↗
Electrical conductor (no.6) insulatedlinear foot$3.00$2.27 – $3.5531Oct 7, 2026, line 40 ↗
Block Soddingsquare yard$8.00$5.08 – $11.2531Sep 3, 2026, line 6 ↗
Pavement surface preparation for marking (6 inch)linear foot$0.26$0.1 – $0.529Sep 3, 2026, line 179 ↗
Electrical conductor (no.8) insulatedlinear foot$2.88$2.00 – $3.1328Oct 7, 2026, line 38 ↗
Reflective pavement marking type i (w)8 inch(solid)(100mil)linear foot$1.45$1.02 – $2.0027Oct 14, 2026, line 11 ↗
Pavement sler 6 inchlinear foot$0.3$0.2 – $0.4527Sep 3, 2026, line 129 ↗
Pavement sler 24 inchlinear foot$1.98$1.03 – $2.9126Sep 3, 2026, line 132 ↗
Reflective pavement marker type ii-a-aeach$5.75$4.70 – $8.7126Sep 3, 2026, line 165 ↗
Temporary sediment control fence (remove)linear foot$1.00$1.00 – $1.5526Oct 7, 2026, line 26 ↗
Tack Coatgallon$4.10$1.53 – $6.0026Oct 14, 2026, line 2 ↗
Conduit (pvc) (sch 80) (2 inch)linear foot$24.00$21.00 – $28.0025Oct 7, 2026, line 23 ↗
Temporary sediment control fence (install)linear foot$4.00$3.10 – $5.0025Oct 7, 2026, line 25 ↗
Pedestrian pole assemblyeach$3,401$2,455 – $3,93224Oct 7, 2026, line 67 ↗
Reflective pavement marking type i (w)24 inch(solid)(100mil)linear foot$8.50$6.54 – $10.7824Oct 7, 2026, line 51 ↗
Reflective pavement marking type i (y)6 inch(solid)(100mil)linear foot$1.00$0.68 – $1.5024Oct 14, 2026, line 14 ↗
Elim ext pm & mrks (8 inch)linear foot$1.17$0.875 – $2.1124Sep 3, 2026, line 169 ↗
Aluminum sign (type a)square foot$41.40$35.11 – $43.5424Oct 7, 2026, line 45 ↗
Ground box type d (162922)w/aproneach$2,418$1,946 – $3,00023Oct 7, 2026, line 43 ↗
Elim ext pm & mrks (6 inch)linear foot$0.8$0.535 – $1.1523Oct 7, 2026, line 55 ↗
Riprap (concrete)(4 in)cubic yard$1,100$723.55 – $1,61123Oct 7, 2026, line 12 ↗
Reflective pavement marking type i (w)6 inch(solid)(100mil)linear foot$1.00$0.67 – $1.3823Oct 14, 2026, line 13 ↗
Trf signal cbl (type c)(12 awg)(2 conductor)linear foot$3.10$2.65 – $3.8023Oct 7, 2026, line 65 ↗
Drill shaft (trf signal pole) (36 in)linear foot$610.60$481.98 – $693.7522Sep 3, 2026, line 11 ↗
Pavement sler 8 inchlinear foot$0.35$0.3 – $0.62322Sep 3, 2026, line 130 ↗
Pavement Sler (Arrow)each$48.00$25.80 – $68.2522Sep 3, 2026, line 133 ↗
Ground box type a (122311)w/aproneach$1,845$1,596 – $2,39222Oct 7, 2026, line 42 ↗
Biodegradable erosion control logs (install) (12 inch)linear foot$5.88$4.05 – $7.8822Oct 7, 2026, line 27 ↗
Elim ext pm & mrks (24 inch)linear foot$4.50$3.00 – $5.8822Sep 3, 2026, line 171 ↗
Downstream Anchor Terminal Sectioneach$1,409$1,235 – $1,97722Oct 7, 2026, line 14 ↗
Riprap (Mow Strip)(4 in)cubic yard$721.20$650.00 – $844.7022Oct 7, 2026, line 4 ↗
Reflective pavement marking type i (w)6 inch(broken)(100mil)linear foot$1.15$0.7 – $1.6522Sep 3, 2026, line 143 ↗
Trf signal cbl (type a)(14 awg)(7 conductor)linear foot$4.00$3.26 – $4.5022Oct 7, 2026, line 63 ↗
Ground Box (Prepare)each$400.00$244.71 – $700.0021Oct 7, 2026, line 78 ↗
Concrete curb (type ii)linear foot$45.00$25.00 – $68.0021Sep 3, 2026, line 23 ↗
Vehicle signal section (12 inch)led(yellow)each$398.00$300.00 – $450.0021Oct 7, 2026, line 59 ↗
Pavement surface preparation for marking (arrow)each$24.00$15.00 – $56.0021Sep 3, 2026, line 183 ↗
Guardrail End Treatment (Install)each$3,448$3,100 – $4,00021Oct 7, 2026, line 16 ↗
Remove Metal Beam Guard Fencelinear foot$3.25$2.60 – $6.2520Oct 6, 2026, line 29 ↗
Vehicle signal section (12 inch)led(red)each$386.50$295.00 – $457.5020Oct 7, 2026, line 60 ↗
Pedestrian signal section (led)(countdown)each$940.00$730.00 – $1,05820Oct 7, 2026, line 61 ↗
Pedestrian detector push button (aps)each$1,115$945.00 – $1,53820Oct 7, 2026, line 68 ↗
Pedestrian detector controller uniteach$4,240$3,835 – $5,37520Oct 7, 2026, line 69 ↗
Remove small road sign support&assemblyeach$121.26$104.50 – $205.2520Oct 7, 2026, line 49 ↗
Elim Ext PM & Mrks (Arrow)each$71.15$56.50 – $101.8820Sep 3, 2026, line 172 ↗
Conduit (Prepare)linear foot$4.27$1.90 – $7.0720Oct 7, 2026, line 26 ↗
Trf signal cbl (type a)(14 awg)(5 conductor)linear foot$3.47$2.95 – $4.0020Sep 3, 2026, line 210 ↗
Trf signal cbl (type a)(14 awg)(20 conductor)linear foot$7.60$6.61 – $11.0020Sep 3, 2026, line 216 ↗
Curb ramp (type 2)each$3,400$2,800 – $4,92019Oct 7, 2026, line 31 ↗
Curb ramp (type 7)each$3,300$2,838 – $4,96219Sep 3, 2026, line 34 ↗
Vehicle signal section (12 inch)led(grn)each$375.00$290.00 – $450.0019Sep 3, 2026, line 199 ↗
Vehicle signal section (12 inch)led(grn arw)each$375.00$290.00 – $458.5019Sep 3, 2026, line 200 ↗
Vehicle signal section (12 inch)led(yellow arw)each$375.00$290.00 – $458.5019Sep 3, 2026, line 202 ↗
Vehicle signal section (12 inch)led(red arw)each$375.00$290.00 – $458.5019Sep 3, 2026, line 204 ↗
Pavement surface preparation for marking (word)each$25.00$17.38 – $66.3919Sep 3, 2026, line 185 ↗
Guardrail End Treatment (Remove)each$309.91$252.50 – $500.0019Oct 6, 2026, line 33 ↗
Drill shaft (trf signal pole) (48 in)linear foot$880.00$555.53 – $950.0019Sep 3, 2026, line 12 ↗
Electrical conductor (no.12) insulatedlinear foot$2.00$1.50 – $2.5219Oct 7, 2026, line 36 ↗
In small road sign support&assembly type10bwg(1)sa(t)each$950.00$814.01 – $1,02019Sep 3, 2026, line 97 ↗
Reflective pavement marking type i (w)12 inch(solid)(100mil)linear foot$4.20$3.25 – $4.9718Oct 14, 2026, line 12 ↗
Conduit (pvc) (sch 40) (2 inch)linear foot$20.51$13.56 – $25.7518Oct 7, 2026, line 33 ↗
Curb ramp (type 1)each$3,181$2,635 – $4,00017Oct 7, 2026, line 30 ↗
Conduit (pvc) (sch 40) (3 inch)linear foot$25.00$20.00 – $27.0017Oct 7, 2026, line 34 ↗