Construction unit costs in Tarrant County, TX

Median awarded unit prices for 75 items on public projects in Tarrant County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Texas › Tarrant County

ItemPerMedianMiddle halfWinning bidsLatest source document
Trench Safetylinear foot$2.00$1.00 – $3.30497Sep 17, 2026, p.1 ↗
Post - CCTV Inspectionlinear foot$3.60$2.41 – $5.00248Sep 16, 2026, p.1 ↗
Manhole Vacuum Testingeach$250.00$200.00 – $500.00237Sep 16, 2026, Open the source page, p.4 ↗
8 inch gate valveeach$2,569$2,250 – $3,200220Sep 16, 2026, p.1 ↗
4' Manholeeach$7,400$4,951 – $10,500205Sep 16, 2026, p.1 ↗
Barrier Free Ramp, Type P- 1each$2,200$1,358 – $2,785195Sep 17, 2026, p.1 ↗
6 inch gate valveeach$2,116$1,780 – $2,771163Sep 14, 2026, p.1 ↗
1 inch water serviceeach$1,989$1,225 – $3,500159Sep 14, 2026, p.1 ↗
2 inch conduit pvc sch 80 (t)linear foot$21.63$15.00 – $29.98150Sep 14, 2026, p.1 ↗
Block Sod Placementsquare yard$8.00$6.00 – $11.95147Sep 17, 2026, p.1 ↗
12 inch gate valveeach$4,810$4,362 – $6,000140Sep 16, 2026, p.1 ↗
2 inch water serviceeach$4,500$3,188 – $6,372140Sep 16, 2026, Open the source page, p.25 ↗
Fire Hydranteach$6,537$5,500 – $7,81786Sep 14, 2026, p.1 ↗
Connection to existing 4 inch- 12 inch watereach$2,500$1,500 – $4,45077Sep 3, 2026, p.1 ↗
Ductile iron water fitting w/ton$10,035$6,000 – $14,13969Sep 16, 2026, p.1 ↗
Concrete Collareach$821.90$512.50 – $1,00062Sep 16, 2026, Open the source page, p.26 ↗
4 inch sewer servicelinear foot$1,253$900.00 – $2,40060Sep 16, 2026, Open the source page, p.5 ↗
4 inch concrete sidewalksquare foot$7.30$5.57 – $10.8859Sep 17, 2026, p.1 ↗
Remove concrete curb & gutterlinear foot$13.00$10.00 – $21.0546Sep 16, 2026, p.1 ↗
Trench Water Stopseach$617.51$350.00 – $1,30045Sep 16, 2026, p.1 ↗
Topsoilcubic yard$28.00$28.00 – $67.6644Sep 17, 2026, p.1 ↗
8 inch sewer pipelinear foot$80.50$64.47 – $116.5044Sep 16, 2026, p.1 ↗
6 inch lime treatmentsquare yard$4.50$4.00 – $10.0044Sep 17, 2026, p.1 ↗
10' Curb Inleteach$4,550$4,000 – $7,88044Sep 17, 2026, p.1 ↗
8 inch water pipelinear foot$62.00$55.28 – $107.0041Sep 16, 2026, p.1 ↗
4 inch- 12 inch pressure plugeach$845.00$500.00 – $1,25040Aug 19, 2026, p.1 ↗
Biodegradable erosion control logs (remove)linear foot$1.25$0.85 – $3.0039Sep 28, 2026, line 17 ↗
4 inch sewer serviceeach$1,100$850.00 – $1,88438Sep 16, 2026, p.1 ↗
4' Storm Junction Boxeach$6,000$5,500 – $7,21437Sep 17, 2026, p.1 ↗
Remove concrete pavementsquare yard$20.25$14.25 – $37.5036Sep 16, 2026, p.1 ↗
Remove Sidewalksquare foot$3.15$2.00 – $5.0034Sep 16, 2026, p.1 ↗
Portable Changeable Message Signday$100.00$50.00 – $153.0633Oct 21, 2026, line 2 ↗
20 inch casing by open cutlinear foot$253.50$223.19 – $304.0632Jul 28, 2026, p.1 ↗
8 inch pvc water pipelinear foot$75.94$59.75 – $104.2532Aug 24, 2026, p.1 ↗
4' Drop Manholeeach$10,500$5,850 – $14,66030Sep 16, 2026, p.1 ↗
15' Curb Inleteach$5,400$5,000 – $8,15030Sep 17, 2026, p.1 ↗
Hydrated Limeton$320.00$252.62 – $370.0028Aug 24, 2026, p.1 ↗
Reflective pavement marking type i (w)8 inch(solid)(100mil)linear foot$1.00$0.857 – $1.5028Oct 21, 2026, line 4 ↗
6 inch pvc water pipelinear foot$76.68$56.00 – $112.8628Aug 27, 2026, p.1 ↗
6 inch concrete curb and gutterlinear foot$30.00$18.25 – $79.7528Aug 24, 2026, p.1 ↗
Reflective pavement marking type i (w)(arrow)(100mil)each$173.40$142.50 – $205.0027Sep 3, 2026, line 23 ↗
Reflective pavement marking type i (w)(word)(100mil)each$183.60$158.00 – $237.5027Sep 3, 2026, line 26 ↗
6 inch water pipelinear foot$91.00$56.50 – $187.7227Sep 14, 2026, p.1 ↗
24 inch reinforced concrete pipe, class iiilinear foot$94.18$85.00 – $106.5027Sep 17, 2026, p.1 ↗
6 inch water linelinear foot$73.00$60.50 – $182.0027Sep 14, 2026, Open the source page, p.4 ↗
6 inch concrete pavementsquare yard$61.73$53.25 – $77.9626Sep 17, 2026, p.1 ↗
Remove asphalt pavementsquare yard$12.00$7.40 – $25.5026Aug 28, 2026, p.1 ↗
Temporary sediment control fence (install)linear foot$3.75$1.00 – $4.5525Sep 28, 2026, line 14 ↗
Temporary sediment control fence (remove)linear foot$1.00$0.9 – $1.9025Sep 28, 2026, line 15 ↗
8 inch lime treatmentsquare yard$5.00$5.00 – $7.5025Sep 17, 2026, p.1 ↗
12 inch pvc water pipelinear foot$104.00$92.00 – $126.0025Aug 27, 2026, p.1 ↗
Furnish/ install aluminum sign groundeach$550.00$375.00 – $650.0025Sep 17, 2026, p.1 ↗
Reflective pavement marking type i (w)24 inch(solid)(100mil)linear foot$7.08$6.57 – $11.0324Sep 3, 2026, line 22 ↗
Reflective pavement marker type ii-c-reach$4.16$4.00 – $6.0024Oct 21, 2026, line 13 ↗
Inlet Protectioneach$250.00$150.00 – $250.0023Sep 17, 2026, p.1 ↗
8 inch sewer pipe, css backfilllinear foot$94.00$84.00 – $146.5023Sep 16, 2026, p.1 ↗
Barrier Free Ramp, Type R- 1each$2,400$2,000 – $2,97223Sep 17, 2026, p.1 ↗
Reflective pavement marker type ii-a-aeach$5.00$4.00 – $6.3822Oct 21, 2026, line 12 ↗
8 inch waterline loweringeach$5,500$4,525 – $6,44822Aug 19, 2026, p.1 ↗
Trench Safety (Co# 1)linear foot$2.00$1.00 – $2.8822Jul 27, 2026, p.1 ↗
8 inch dip sewer pipelinear foot$132.87$100.00 – $149.5022Aug 19, 2026, p.1 ↗
Furnish/ Install Led Lighting Fixtureeach$792.50$397.87 – $1,17522Aug 12, 2026, p.1 ↗
Roadway illumination foundation type 1, 2, and 4each$1,684$1,200 – $2,16921Sep 17, 2026, p.1 ↗
5' Storm Junction Boxeach$8,232$7,000 – $11,50021Sep 17, 2026, p.1 ↗
Biodegradable erosion control logs (install) (8 inch)linear foot$4.50$1.90 – $7.5621Sep 28, 2026, line 16 ↗
Concrete Collar For Manholeeach$1,000$750.00 – $1,25021Sep 16, 2026, p.1 ↗
Pavement sler 6 inchlinear foot$0.215$0.165 – $0.47520Sep 28, 2026, line 20 ↗
Connection to existing 16 inch water maineach$6,154$4,500 – $10,17320Sep 16, 2026, p.1 ↗
12 inch water pipelinear foot$125.16$102.00 – $177.4320Sep 16, 2026, p.1 ↗
Lane Legend Arroweach$400.00$243.19 – $477.5020Aug 21, 2026, p.1 ↗
Utility Service Surface Restorationsquare yard$5.50$3.70 – $12.7520Jul 9, 2026, p.1 ↗
No 10 insulated electrical conductorlinear foot$4.15$1.97 – $5.1420Aug 12, 2026, p.1 ↗
6 inch sewer pipelinear foot$132.63$75.00 – $213.1520Aug 18, 2026, p.1 ↗
Guardrail End Treatment (Install)each$3,050$2,988 – $3,50020Oct 7, 2026, line 7 ↗
Block Soddingsquare yard$9.40$5.58 – $12.0018Aug 6, 2026, line 5 ↗