Granular Embankment (Cv) (P): cost per cubic yard in St. Louis County, MN
The median awarded price is $25.00 per cubic yard, from 25 winning bids on 19 public projects in St. Louis County, MN (2023–2026). Half of the awarded prices fall between $21.00 and $30.00.
Cost by state › Minnesota › St. Louis County › Granular Embankment (Cv) (P)
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $22.50 in 2022 to $30.00 in 2026 (+33%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2022 | $22.50 | 7 |
| 2023 | $25.00 | 5 |
| 2024 | $15.00 | 5 |
| 2025 | $25.00 | 11 |
| 2026 | $30.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 4, 2026 | St. Louis County | 40 CU YD | $30.00 | Open bid tab, CP 0084-880514, SP 0 ↗ |
| Jun 4, 2026 | St. Louis County | 902 CU YD | $24.65 | Open bid tab, CP 0098-477576 ↗ |
| Apr 30, 2026 | St. Louis County | 13 CU YD | $30.00 | Open bid tab, CP 0133-300209 ↗ |
| Jan 29, 2026 | St. Louis County | 285 CU YD | $19.50 | Open bid tab, CP 0021-556743 ↗ |
| Jan 8, 2026 | St. Louis County | 318 CU YD | $35.50 | Open bid tab, CP 0266-778356 ↗ |
See every awarded price for this item on the Granular Embankment (Cv) (P) item page.
Related items in St. Louis County
- Structure Excavation Class E (P): $16.00 per cubic yard
- Grubbing: $8,901 per acre
- Granular Backfill (Cv) (P): $32.00 per cubic yard
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Base Stabilization (Base One): $0.91 per square yard