Earthwork · awarded bid prices · St. Louis County
Granular Backfill (Cv) (P): cost per cubic yard in St. Louis County, MN
The median awarded price is $32.00 per cubic yard, from 49 winning bids on 15 public projects in St. Louis County, MN (2024–2026). Half of the awarded prices fall between $28.20 and $40.00.
Cost by state › Minnesota › St. Louis County › Granular Backfill (Cv) (P)
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $21.69 in 2022 to $31.23 in 2026 (+44%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2022 | $21.69 | 10 |
| 2023 | $21.50 | 13 |
| 2024 | $27.30 | 14 |
| 2025 | $40.00 | 22 |
| 2026 | $31.23 | 13 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 9, 2026 | St. Louis County | 2035 CU YD | $31.07 | Open bid tab, CP 0091-442363 ↗ |
| May 7, 2026 | St. Louis County | 4420 CU YD | $29.82 | Open bid tab, CP 0100-556174 ↗ |
| Mar 5, 2026 | St. Louis County | 2962 CU YD | $29.09 | Open bid tab, CP 0045-659060 ↗ |
| Feb 5, 2026 | St. Louis County | 1121 CU YD | $26.55 | Open bid tab, CP 0013-458864 ↗ |
| May 29, 2025 | St. Louis County | 83 CU YD | $40.00 | Open bid tab, CP 0057-885433 ↗ |
See every awarded price for this item on the Granular Backfill (Cv) (P) item page.
Related items in St. Louis County
- Structure Excavation Class E (P): $16.00 per cubic yard
- Grubbing: $8,901 per acre
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Base Stabilization (Base One): $0.91 per square yard
- Common Embankment (Cv): $9.50 per cubic yard