The median awarded price is $8,901 per acre, from 49 winning bids on 29 public projects in St. Louis County, MN (2023–2026). Half of the awarded prices fall between $7,300 and $12,000.
Cost by state › Minnesota › St. Louis County › Grubbing
Winning bids only, as printed in the agencies' bid tabulations (MnDOT, St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $6,000 in 2022 to $8,901 in 2026 (+48%).
| Year | Median per acre | Winning bids |
|---|---|---|
| 2022 | $6,000 | 9 |
| 2023 | $7,875 | 18 |
| 2024 | $9,500 | 18 |
| 2025 | $8,600 | 17 |
| 2026 | $8,901 | 11 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 6, 2026 | St. Louis County | 12.6 ACRE | $7,300 | Open bid tab, CP 0000-776409 ↗ |
| Jun 11, 2026 | St. Louis County | 0.14 ACRE | $8,500 | Open bid tab, CP 0088-885444 ↗ |
| May 7, 2026 | St. Louis County | 0.35 ACRE | $14,093 | Open bid tab, CP 0100-556174 ↗ |
| Mar 12, 2026 | St. Louis County | 2.1 ACRE | $9,373 | Open bid tab, CP 0142-860298 ↗ |
| Mar 5, 2026 | St. Louis County | 0.1 ACRE | $25,486 | Open bid tab, CP 0045-659060 ↗ |
The same item across Minnesota: statewide figures. See every awarded price for this item on the Grubbing item page.
Related items in St. Louis County
- Structure Excavation Class E (P): $16.00 per cubic yard
- Granular Backfill (Cv) (P): $32.00 per cubic yard
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Base Stabilization (Base One): $0.91 per square yard
- Common Embankment (Cv): $9.50 per cubic yard