Earthwork · awarded bid prices · St. Louis County
Structure Excavation Class E (P): cost per cubic yard in St. Louis County, MN
The median awarded price is $16.00 per cubic yard, from 51 winning bids on 16 public projects in St. Louis County, MN (2024–2026). Half of the awarded prices fall between $11.47 and $20.50.
Cost by state › Minnesota › St. Louis County › Structure Excavation Class E (P)
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $12.66 in 2022 to $22.26 in 2026 (+76%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2022 | $12.66 | 12 |
| 2023 | $16.50 | 10 |
| 2024 | $12.50 | 15 |
| 2025 | $14.72 | 22 |
| 2026 | $22.26 | 14 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 9, 2026 | St. Louis County | 210 CU YD | $49.63 | Open bid tab, CP 0091-442363 ↗ |
| May 7, 2026 | St. Louis County | 101 CU YD | $43.39 | Open bid tab, CP 0100-556174 ↗ |
| Mar 5, 2026 | St. Louis County | 4585 CU YD | $16.03 | Open bid tab, CP 0045-659060 ↗ |
| Feb 5, 2026 | St. Louis County | 1203 CU YD | $12.99 | Open bid tab, CP 0013-458864 ↗ |
| Sep 11, 2025 | St. Louis County | 6 CU YD | $100.00 | Open bid tab, CP 0102-833621 ↗ |
See every awarded price for this item on the Structure Excavation Class E (P) item page.
Related items in St. Louis County
- Grubbing: $8,901 per acre
- Granular Backfill (Cv) (P): $32.00 per cubic yard
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Base Stabilization (Base One): $0.91 per square yard
- Common Embankment (Cv): $9.50 per cubic yard