Earthwork · awarded bid prices · St. Louis County
Base Stabilization (Base One): cost per square yard in St. Louis County, MN
The median awarded price is $0.91 per square yard, from 30 winning bids on 11 public projects in St. Louis County, MN (2023–2026). Half of the awarded prices fall between $0.712 and $1.36.
Cost by state › Minnesota › St. Louis County › Base Stabilization (Base One)
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $0.36 in 2022 to $1.42 in 2026 (+296%).
| Year | Median per square yard | Winning bids |
|---|---|---|
| 2022 | $0.36 | 20 |
| 2023 | $0.57 | 7 |
| 2025 | $0.9 | 13 |
| 2026 | $1.42 | 10 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 18, 2026 | St. Louis County | 1416 SQ YD | $3.20 | Open bid tab, CP 0305-556182 ↗ |
| Jun 11, 2026 | St. Louis County | 199978 SQ YD | $1.50 | Open bid tab, CP 0021-439116; SP 0 ↗ |
| Jun 4, 2026 | St. Louis County | 130169 SQ YD | $1.65 | Open bid tab, CP 0098-477576 ↗ |
| Jan 15, 2026 | St. Louis County | 14609 SQ YD | $1.40 | Open bid tab, CP 0058-836966 ↗ |
| Dec 18, 2025 | St. Louis County | 36718 SQ YD | $0.9 | Open bid tab, CP 0010-603328 ↗ |
See every awarded price for this item on the Base Stabilization (Base One) item page.
Related items in St. Louis County
- Structure Excavation Class E (P): $16.00 per cubic yard
- Grubbing: $8,901 per acre
- Granular Backfill (Cv) (P): $32.00 per cubic yard
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Common Embankment (Cv): $9.50 per cubic yard