Earthwork · awarded bid prices · St. Louis County
Common Embankment (Cv) (P): cost per cubic yard in St. Louis County, MN
The median awarded price is $11.00 per cubic yard, from 26 winning bids on 21 public projects in St. Louis County, MN (2024–2026). Half of the awarded prices fall between $7.51 and $17.95.
Cost by state › Minnesota › St. Louis County › Common Embankment (Cv) (P)
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $8.75 in 2022 to $11.80 in 2026 (+35%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2022 | $8.75 | 8 |
| 2023 | $8.50 | 6 |
| 2024 | $13.00 | 6 |
| 2025 | $8.62 | 8 |
| 2026 | $11.80 | 12 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 6, 2026 | St. Louis County | 28872 CU YD | $13.60 | Open bid tab, CP 0000-776409 ↗ |
| Jul 9, 2026 | St. Louis County | 1520 CU YD | $7.55 | Open bid tab, CP 0091-442363 ↗ |
| Jun 18, 2026 | St. Louis County | 205 CU YD | $10.00 | Open bid tab, CP 0305-556182 ↗ |
| May 7, 2026 | St. Louis County | 1123 CU YD | $17.81 | Open bid tab, CP 0100-556174 ↗ |
| Mar 12, 2026 | St. Louis County | 50984 CU YD | $7.59 | Open bid tab, CP 0142-860298 ↗ |
See every awarded price for this item on the Common Embankment (Cv) (P) item page.
Related items in St. Louis County
- Structure Excavation Class E (P): $16.00 per cubic yard
- Grubbing: $8,901 per acre
- Granular Backfill (Cv) (P): $32.00 per cubic yard
- Excavation Common **P**: $15.00 per cubic yard
- Common Topsoil Borrow: $24.68 per cubic yard
- Excavation Common: $15.00 per cubic yard
- Select Granular Embankment Mod 7% (Cv) (P): $23.80 per cubic yard
- Base Stabilization (Base One): $0.91 per square yard