| Substructure Repair (Unformed) | square foot | $177.25 | $160.00 – $241.00 | 61 | Dec 12, 2025, Open the source page, contract 251212-F01 |
| Half-sole Repair | square foot | $158.00 | $98.50 – $175.00 | 57 | Oct 17, 2025, Open the source page, contract 251017-F05 |
| Silt Fence | linear foot | $3.05 | $2.88 – $3.76 | 47 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Truck or Trailer Mounted Attenuator (Tma) | each | $2,500 | $1,688 – $5,000 | 46 | Mar 15, 2024, Open the source page, contract 240315-F03 |
| Preformed Thermoplastic Pavement Marking, 24 in. White | linear foot | $20.00 | $18.00 – $25.00 | 45 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Preformed Thermoplastic Pavement Marking, Left/Right Arrow | each | $280.00 | $280.00 – $300.00 | 43 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Sh-flat Sheet | square foot | $36.00 | $28.82 – $40.00 | 42 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Pull Box, Preformed Class 1 | each | $1,610 | $1,512 – $1,701 | 39 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Shf-flat Sheet Fluorescent | square foot | $38.06 | $34.85 – $44.00 | 38 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Type 5 Aggregate for Base (4 in. Thick) | square yard | $12.00 | $10.00 – $15.00 | 37 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Substructure Repair (Formed) | square foot | $210.00 | $168.00 – $275.00 | 37 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Coldmilling asphalt pavement for remove of surfacing (3 in. thick or less) | square yard | $3.25 | $2.75 – $4.36 | 36 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Type A Crashworthy End Terminal (Mash) | each | $3,900 | $3,800 – $4,009 | 36 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Concrete Sidewalk, 4 in. | square yard | $74.20 | $58.00 – $100.84 | 35 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Truncated Domes | square foot | $27.10 | $22.25 – $30.00 | 35 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Cable, 16 AWG 2 Conductor | linear foot | $1.42 | $1.10 – $1.77 | 34 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Cable, 10 AWG 1 Conductor, Pole and Bracket | linear foot | $1.05 | $0.762 – $1.25 | 34 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Pull Box, Preformed Class 2 | each | $2,340 | $2,200 – $2,490 | 34 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Base, Concrete | cubic yard | $2,452 | $1,973 – $2,856 | 34 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Reinforced steel (epoxy coated) | pound | $3.00 | $2.08 – $4.04 | 34 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Changeable message sign without communication interface, con tractor furnish, contractor retained | each | $2,500 | $2,000 – $3,288 | 34 | Apr 18, 2025, Open the source page, contract 250418-F02 |
| Cable, 16 AWG 5 Conductor | linear foot | $1.75 | $1.50 – $2.06 | 33 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| MGS Guardrail | linear foot | $29.50 | $28.00 – $35.25 | 32 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Sh-flat Sheet - Signal Sign | square foot | $38.00 | $36.19 – $43.92 | 31 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Curb Inlet Check | each | $120.00 | $50.00 – $131.88 | 31 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| 6 In. White High Build Waterborne Pavement Marking Paint, Type L Beads | linear foot | $0.32 | $0.28 – $0.55 | 31 | Apr 18, 2025, Open the source page, contract 250418-F02 |
| Pavement marking remove | linear foot | $1.00 | $0.85 – $2.21 | 31 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Signal Sign, Mounting Hardware | each | $250.00 | $170.50 – $315.00 | 31 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Preformed Thermoplastic Pavement Marking, Combination Str/Lt/Rt | each | $450.00 | $412.50 – $500.00 | 30 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Concrete Curb (6 in. Height and Under) Type S | linear foot | $52.00 | $41.00 – $84.50 | 30 | May 15, 2026, Open the source page, contract 260515-F02 |
| Turf Type Tall Fescue Sodding | square yard | $13.00 | $12.00 – $16.00 | 30 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Post, Signal 8 FT. | each | $1,226 | $1,150 – $1,321 | 30 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| MGS End Anchor | each | $2,000 | $1,800 – $2,111 | 30 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Conduit, 3 in., Trench with Tracer Wire | linear foot | $17.44 | $16.00 – $19.00 | 30 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Concrete Footings, Embedded | cubic yard | $3,200 | $2,800 – $3,600 | 29 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| 6 In. Concrete Median Strip | square yard | $140.00 | $122.50 – $170.00 | 29 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Full deep pavement repair saw cut (for perimeter and internal saw cuts) | linear foot | $10.00 | $7.00 – $12.00 | 29 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| 2 In. Psst Post - 12 GA. | linear foot | $30.00 | $27.00 – $32.00 | 29 | Apr 17, 2026, Open the source page, contract 260417-F02 |
| Cable, 16 AWG 7 Conductor | linear foot | $2.15 | $2.00 – $2.50 | 28 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Conduit, 3 in., Pushed with Tracer Wire | linear foot | $33.00 | $25.12 – $40.13 | 28 | May 15, 2026, Open the source page, contract 260515-F02 |
| Clean and epoxy coating | square foot | $14.00 | $8.00 – $32.50 | 27 | Aug 15, 2025, Open the source page, contract 250815-F01 |
| Pull Box, Preformed Class 3 | each | $3,140 | $2,868 – $3,352 | 27 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Paved Approach, 8 in. | square yard | $115.00 | $104.00 – $127.00 | 27 | May 15, 2026, Open the source page, contract 260515-F02 |
| Silicone expansion joint seal | linear foot | $42.00 | $42.00 – $61.50 | 27 | Nov 15, 2024, Open the source page, contract 241115-F03 |
| Furnishing and placing concrete material for full deep pavement repair | square yard | $365.00 | $283.50 – $432.50 | 27 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Dowel bar (drilling, furnishing and install) for full deep pavement repair | each | $7.00 | $5.00 – $15.00 | 27 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Misc.countdown Pedestrian Signal Head, Type 1S | each | $661.00 | $644.75 – $710.27 | 26 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Pipe post | pound | $8.25 | $6.12 – $10.00 | 26 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Signal Head, Type 3B | each | $1,266 | $1,194 – $1,401 | 26 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Mulching | acre | $2,662 | $1,800 – $5,350 | 25 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Temporary traffic barrier, contractor furnish / retained | linear foot | $25.00 | $21.00 – $31.05 | 25 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Diamond Grinding | square yard | $10.50 | $10.25 – $11.50 | 25 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Seeding - Cool Season Grasses | acre | $5,000 | $3,000 – $7,500 | 25 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Signal Head, Type 4B | each | $1,482 | $1,395 – $1,575 | 25 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| 2.5 In. Psst Post - 12 GA. | linear foot | $33.00 | $30.00 – $38.00 | 25 | Apr 17, 2026, Open the source page, contract 260417-F02 |
| Preformed Thermoplastic Pavement Marking, Straight Arrow | each | $250.00 | $200.00 – $250.00 | 25 | May 15, 2026, Open the source page, contract 260515-F02 |
| Open Cell Foam Joint Seal | linear foot | $110.00 | $100.00 – $131.00 | 24 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Slope Protection | square yard | $116.50 | $98.00 – $197.75 | 24 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Remove of existing deck repair | square foot | $22.00 | $22.00 – $38.70 | 24 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Asphalt pavement mixture pg64-22, (bp-1) | ton | $135.00 | $105.97 – $172.50 | 24 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Cable-conduit, 1 in., 2 Conductors and 1 Bare Neutral, 8 AWG | linear foot | $5.60 | $4.57 – $6.09 | 24 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Full deep repair | square foot | $215.00 | $195.56 – $280.00 | 24 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Field Application of Inorganic Zinc Primer | square foot | $3.50 | $2.00 – $4.00 | 24 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Controller Assembly Housing, Nema TS2 Controller | each | $21,058 | $19,562 – $22,996 | 24 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Culvert Cleanout | each | $1,950 | $1,348 – $4,321 | 24 | May 15, 2026, Open the source page, contract 260515-F02 |
| 6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beads | linear foot | $0.33 | $0.28 – $0.488 | 24 | Apr 18, 2025, Open the source page, contract 250418-F03 |
| Preformed Thermoplastic Pavement Marking, 12 in White, Yield Line Triangles | each | $65.00 | $22.50 – $66.62 | 23 | May 16, 2025, Open the source page, contract 250516-F01 |
| Supplementary Wearing Surface Material | cubic yard | $700.00 | $700.00 – $700.00 | 23 | Dec 12, 2025, Open the source page, contract 251212-F01 |
| Misc.epoxy Urethane Polymer Wearing Surface With Healer/sealer | square yard | $41.00 | $38.67 – $44.00 | 23 | May 16, 2025, Open the source page, contract 250516-F01 |
| Impact Attenuator (Relocation) | each | $1,000 | $759.00 – $1,078 | 23 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Class B-2 Concrete | cubic yard | $4,500 | $4,500 – $5,125 | 23 | Nov 14, 2025, Open the source page, contract 251114-F08 |
| Trench type i | linear foot | $6.42 | $6.00 – $7.94 | 23 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Latex Modified Concrete Wearing Surface | square yard | $138.00 | $130.00 – $140.00 | 23 | Dec 12, 2025, Open the source page, contract 251212-F01 |
| Rock Ditch Check | linear foot | $20.00 | $14.00 – $42.50 | 23 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Type 5 Aggregate for Base (6 in. Thick) | square yard | $16.00 | $11.75 – $20.00 | 23 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| St-structure | square foot | $36.00 | $35.00 – $42.00 | 23 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Total Surface Hydro Demolition | square yard | $48.00 | $48.00 – $58.00 | 23 | Dec 12, 2025, Open the source page, contract 251212-F01 |
| Misc.atc Traffic Signal Controller | each | $5,494 | $5,262 – $5,779 | 22 | Jun 18, 2026, Open the source page, contract 260618-F01 |
| Misc.sl District Traffic Signal Detection System | each | $38,234 | $34,300 – $43,471 | 22 | May 15, 2026, Open the source page, contract 260515-F02 |
| Driven Post Anchor for 2 in. Psst - 12 GA. | each | $280.69 | $231.25 – $323.88 | 22 | May 15, 2026, Open the source page, contract 260515-F02 |