| Construction sign | square foot | $6.67 | $6.00 – $8.23 | 44 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Channelizer (Trim Line) | each | $19.30 | $15.00 – $27.25 | 42 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Flashing Arrow Panel | each | $973.21 | $750.00 – $1,646 | 37 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Sediment remove | cubic yard | $53.00 | $30.62 – $95.80 | 24 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Pavement marking remove | linear foot | $0.66 | $0.538 – $2.01 | 24 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Seeding - Cool Season Grasses | acre | $3,300 | $2,486 – $7,370 | 23 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Preformed Thermoplastic Pavement Marking, 24 in. White | linear foot | $23.00 | $20.00 – $24.00 | 23 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Mulching | acre | $2,850 | $1,852 – $4,745 | 22 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Type A Crashworthy End Terminal (Mash) | each | $3,285 | $2,914 – $3,696 | 22 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Sequential Flashing Warning Light | each | $65.00 | $50.00 – $75.00 | 21 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Changeable message sign without communication interface, con tractor furnish, contractor retained | each | $2,900 | $2,000 – $4,800 | 21 | Apr 18, 2025, Open the source page, contract 250418-C03 |
| 6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beads | linear foot | $0.27 | $0.26 – $0.425 | 20 | Mar 14, 2025, Open the source page, contract 250314-C07 |
| Silt Fence | linear foot | $3.65 | $2.50 – $6.83 | 19 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| MGS Guardrail | linear foot | $28.75 | $23.76 – $30.80 | 19 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Tack Coat | gallon | $3.00 | $2.89 – $3.75 | 17 | Apr 17, 2026, Open the source page, contract 260417-C07 |
| Preformed Thermoplastic Pavement Marking, Left/Right Arrow | each | $265.00 | $247.50 – $350.00 | 17 | May 15, 2026, Open the source page, contract 260515-C14 |
| Compacting Embankment | cubic yard | $10.64 | $4.42 – $14.71 | 16 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| 6 In. White High Build Waterborne Pavement Marking Paint, Type L Beads | linear foot | $0.26 | $0.26 – $0.285 | 16 | Jun 20, 2025, Open the source page, contract 250620-C04 |
| Coldmilling asphalt pavement for remove of surfacing (3 in. thick or less) | square yard | $3.16 | $2.68 – $7.25 | 15 | Apr 17, 2026, Open the source page, contract 260417-C07 |
| Class A Excavation | cubic yard | $42.54 | $19.91 – $78.62 | 15 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Class 3 Excavation | cubic yard | $40.17 | $16.00 – $69.70 | 14 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Type III Moveable Barricade | each | $135.00 | $100.50 – $162.50 | 14 | Apr 18, 2025, Open the source page, contract 250418-C03 |
| Type 5 Aggregate for Base (6 in. Thick) | square yard | $20.62 | $19.51 – $32.70 | 14 | May 15, 2026, Open the source page, contract 260515-C14 |
| Rock Ditch Check | linear foot | $50.00 | $25.00 – $100.75 | 13 | May 15, 2026, Open the source page, contract 260515-C08 |
| Curb Inlet Check | each | $130.00 | $100.00 – $145.00 | 13 | Apr 17, 2026, Open the source page, contract 260417-C02 |
| Advanced Warning Rail System | each | $54.09 | $50.00 – $66.34 | 12 | Jun 20, 2025, Open the source page, contract 250620-C04 |
| Temporary traffic barrier, contractor furnish / retained | linear foot | $32.98 | $23.00 – $39.54 | 12 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Type 5 Aggregate for Base (4 in. Thick) | square yard | $17.23 | $14.26 – $30.84 | 12 | Jun 18, 2026, Open the source page, contract 260618-C02 |
| Reinforced steel (epoxy coated) | pound | $2.39 | $1.97 – $4.28 | 12 | Jun 18, 2026, Open the source page, contract 260618-C02 |