Sanitary Sewer · awarded bid prices · Hennepin County

Connect to Existing Storm Sewer: cost per each in Hennepin County, MN

The median awarded price is $1,307 per each, from 18 winning bids on 18 public projects in Hennepin County, MN (2024–2026). Half of the awarded prices fall between $1,202 and $1,500.

Cost by state › Minnesota › Hennepin County › Connect to Existing Storm Sewer

$1,307median per each
$1,202 – $1,500middle half (25th–75th percentile)
18winning bids, 18 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (MnDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $930.50 in 2020 to $1,300 in 2025 (+40%).

YearMedian per eachWinning bids
2020$930.506
2022$1,1105
2023$1,3636
2024$950.007
2025$1,3007

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Jun 10, 2026MnDOT7 EACH$2,000Open the source page, contract 260089
Mar 25, 2026MnDOT1 EACH$1,311Open the source page, contract 260025
Mar 25, 2026MnDOT1 EACH$1,400Open the source page, contract 260038
Mar 17, 2026MnDOT83 EACH$2,000Open the source page, contract 260033
Jun 11, 2025MnDOT22 EACH$1,500Open the source page, contract 250061

The same item across Minnesota: statewide figures. See every awarded price for this item on the Connect to Existing Storm Sewer item page.