Other · awarded bid prices · Hennepin County
Truncated Domes: cost per square foot in Hennepin County, MN
The median awarded price is $62.00 per square foot, from 17 winning bids on 17 public projects in Hennepin County, MN (2024–2026). Half of the awarded prices fall between $56.70 and $68.04.
Cost by state › Minnesota › Hennepin County › Truncated Domes
Winning bids only, as printed in the agencies' bid tabulations (MnDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $62.00 in 2020 to $68.04 in 2026 (+10%).
| Year | Median per square foot | Winning bids |
|---|---|---|
| 2020 | $62.00 | 7 |
| 2021 | $54.00 | 5 |
| 2023 | $60.00 | 5 |
| 2024 | $59.50 | 6 |
| 2025 | $55.80 | 6 |
| 2026 | $68.04 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 10, 2026 | MnDOT | 48 S F | $85.00 | Open the source page, contract 260089 |
| Mar 25, 2026 | MnDOT | 124 S F | $68.04 | Open the source page, contract 260025 |
| Mar 25, 2026 | MnDOT | 569 S F | $70.00 | Open the source page, contract 260038 |
| Mar 17, 2026 | MnDOT | 246 S F | $62.00 | Open the source page, contract 260033 |
| Feb 25, 2026 | MnDOT | 231 S F | $65.00 | Open the source page, contract 260008 |
The same item across Minnesota: statewide figures. See every awarded price for this item on the Truncated Domes item page.
Related items in Hennepin County
- Drill and Grout Reinf Bar (Epoxy Coated): $13.55 per each
- Casting Assembly: $1,175 per each
- Remove Energy Absorbing Terminal: $600.00 per each
- End Treatment-tangent Terminal: $4,000 per each
- Remove Anchorage Assembly-plate Beam: $325.00 per each
- Reinforcement Bars (Epoxy Coated): $1.80 per pound
- 6" Solid Line Multi-component Ground IN (wr): $2.25 per linear foot
- Pull Vault: $2,930 per each