Street Lighting · awarded bid prices · Miami-dade County
Light Pole Complete, Remove: cost per each in Miami-dade County, FL
The median awarded price is $1,000 per each, from 23 winning bids on 23 public projects in Miami-dade County, FL (2021–2026). Half of the awarded prices fall between $913.11 and $1,254.
Cost by state › Florida › Miami-dade County › Light Pole Complete, Remove
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $570.00 in 2019 to $1,000 in 2023 (+75%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $570.00 | 9 |
| 2021 | $683.00 | 7 |
| 2022 | $1,000 | 7 |
| 2023 | $1,000 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 30, 2026 | FDOT | 31 EA | $1,020 | Open bid tab, T6398 ↗ |
| Sep 30, 2026 | FDOT | 1 EA | $1,000 | Open bid tab, T6613 ↗ |
| Dec 3, 2025 | FDOT | 2 EA | $707.18 | Open bid tab, T6615 ↗ |
| Oct 29, 2025 | FDOT | 1 EA | $688.27 | Open bid tab, T6621 ↗ |
| Jul 30, 2025 | FDOT | 1 EA | $2,209 | Open bid tab, T6599 ↗ |
See every awarded price for this item on the Light Pole Complete, Remove item page.
Related items in Miami-dade County
- Pull & Splice Box, F&I, 13" x 24": $1,700 per each
- Conduit, Furnish & Install: $39.50 per linear foot
- Prestressed Concrete Pole, F&I: $2,973 per each
- Lighting Conductors, F&I: $4.65 per linear foot
- Electrical Service Wire, Furnish: $10.00 per linear foot
- Pull & Splice Box, Install: $1,076 per each
- Pull & Splice Box, F&I, 24" x 36": $2,649 per each
- Aluminum Signals Pole, Pedestal: $2,235 per each