Street Lighting · awarded bid prices · Miami-dade County
Prestressed Concrete Pole, F&I: cost per each in Miami-dade County, FL
The median awarded price is $2,973 per each, from 58 winning bids on 35 public projects in Miami-dade County, FL (2023–2026). Half of the awarded prices fall between $2,551 and $3,470.
Cost by state › Florida › Miami-dade County › Prestressed Concrete Pole, F&I
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1,955 in 2021 to $2,551 in 2026 (+30%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2021 | $1,955 | 13 |
| 2022 | $1,977 | 10 |
| 2023 | $3,174 | 18 |
| 2024 | $3,176 | 21 |
| 2025 | $2,990 | 21 |
| 2026 | $2,551 | 13 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 30, 2026 | FDOT | 1 EA | $2,551 | Open bid tab, T6398 ↗ |
| Sep 30, 2026 | FDOT | 2 EA | $2,800 | Open bid tab, T6613 ↗ |
| Jul 29, 2026 | FDOT | 2 EA | $3,000 | Open bid tab, T6595 ↗ |
| Jul 29, 2026 | FDOT | 1 EA | $2,500 | Open bid tab, T6625 ↗ |
| Mar 25, 2026 | FDOT | 2 EA | $2,500 | Open bid tab, T6589 ↗ |
The same item across Florida: statewide figures. See every awarded price for this item on the Prestressed Concrete Pole, F&I item page.
Related items in Miami-dade County
- Pull & Splice Box, F&I, 13" x 24": $1,700 per each
- Conduit, Furnish & Install: $39.50 per linear foot
- Lighting Conductors, F&I: $4.65 per linear foot
- Electrical Service Wire, Furnish: $10.00 per linear foot
- Pull & Splice Box, Install: $1,076 per each
- Pull & Splice Box, F&I, 24" x 36": $2,649 per each
- Aluminum Signals Pole, Pedestal: $2,235 per each
- Pole Cable Distribution System: $1,000 per each