Pull & Splice Box, Install: cost per each in Miami-dade County, FL
The median awarded price is $1,076 per each, from 39 winning bids on 27 public projects in Miami-dade County, FL (2024–2026). Half of the awarded prices fall between $1,000 and $1,237.
Cost by state › Florida › Miami-dade County › Pull & Splice Box, Install
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1,200 in 2024 to $1,100 in 2026 (-8%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2024 | $1,200 | 12 |
| 2025 | $1,076 | 15 |
| 2026 | $1,100 | 12 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 30, 2026 | FDOT | 1 EA | $1,224 | Open bid tab, T6398 ↗ |
| Sep 30, 2026 | FDOT | 2 EA | $1,000 | Open bid tab, T6613 ↗ |
| Jul 29, 2026 | FDOT | 2 EA | $725.00 | Open bid tab, T6595 ↗ |
| Jul 29, 2026 | FDOT | 1 EA | $1,200 | Open bid tab, T6625 ↗ |
| Mar 25, 2026 | FDOT | 2 EA | $1,200 | Open bid tab, T6589 ↗ |
See every awarded price for this item on the Pull & Splice Box, Install item page.
Related items in Miami-dade County
- Pull & Splice Box, F&I, 13" x 24": $1,700 per each
- Conduit, Furnish & Install: $39.50 per linear foot
- Prestressed Concrete Pole, F&I: $2,973 per each
- Lighting Conductors, F&I: $4.65 per linear foot
- Electrical Service Wire, Furnish: $10.00 per linear foot
- Pull & Splice Box, F&I, 24" x 36": $2,649 per each
- Aluminum Signals Pole, Pedestal: $2,235 per each
- Pole Cable Distribution System: $1,000 per each