ItemPerMedianMiddle halfWinning bids
Planing Bituminous Pavementsquare yard$5.00$3.00 – $12.75101
Crushed Surfacing Base Courseton$55.50$40.00 – $81.0096
ESC Leadday$150.00$87.50 – $250.0095
Inlet Protectioneach$140.00$110.00 – $200.0093
Construction Signs Class Asquare foot$31.50$23.00 – $50.0090
Temporary Pavement Marking-short Durationlinear foot$0.55$0.3 – $1.2589
Flexible Guide Posteach$76.00$57.00 – $105.0085
HMA Sawcut and Seallinear foot$40.00$30.00 – $49.2566
Portable Changeable Message Signhour$7.00$4.77 – $12.0064
Roadway Excavation Incl. Haulcubic yard$50.00$30.70 – $91.5063
Plastic Drainage Markingeach$101.60$85.75 – $142.5056
Pavement Repair Excavation Incl. Haulsquare yard$20.00$9.75 – $45.2551
Plastic Traffic Arroweach$457.55$360.00 – $674.2550
Beam Guardrail Type 31linear foot$47.16$43.00 – $57.0050
Beam Guardrail Type 31 Non-flared Terminaleach$5,205$4,622 – $6,00048
Plastic Stop Linelinear foot$26.00$18.50 – $40.0047
Plastic Linelinear foot$3.90$2.00 – $6.5043
Removing Guardraillinear foot$10.00$8.00 – $14.1242
Plastic Wide Linelinear foot$6.05$4.50 – $9.7542
High Visibility Fencelinear foot$6.35$4.50 – $8.0041
Clearing AND Grubbingacre$25,000$13,250 – $51,41640
HMA CL. 1/2 in. PG 58H-22ton$149.72$122.00 – $183.7538
Structure Excavation Class B Incl. Haulcubic yard$30.00$18.00 – $88.9137
Embankment Compactioncubic yard$11.00$8.03 – $21.0036
Plastic Crosswalk Linesquare foot$14.12$11.28 – $20.7534
Removing Guardrail Anchoreach$407.50$318.25 – $550.2534
Temporary Barrierlinear foot$50.08$36.25 – $84.6232
Cement Conc. Sidewalksquare yard$92.50$71.26 – $169.2532
Asphalt for Fog Sealton$1,000$925.00 – $1,45031
High Visibility Silt Fencelinear foot$6.50$5.75 – $8.6531
Extruded Curblinear foot$33.51$25.54 – $67.5030
Detectable Warning Surfacesquare foot$50.00$35.00 – $80.0029
Shoring or Extra Excavation Class Bsquare foot$2.00$1.00 – $5.0029
Plastic Crosshatch Markinglinear foot$11.12$8.79 – $14.2528
Commercial HMAton$292.50$177.50 – $400.0028
HMA CL. 3/8 IN. PG 64H-28ton$130.00$99.90 – $153.0027
Painted Drainage Markingeach$50.00$37.00 – $65.0025
Temporary Impact Attenuatoreach$5,300$4,500 – $6,50025
Flaggershour$85.50$76.25 – $98.2522
Other Traffic Control Laborhour$94.25$80.00 – $110.0021
Silt Fencelinear foot$7.00$6.31 – $10.0418