| Spcc Plan | ls | 5 | $566.74 | $300.00 | $300.00 – $3,000 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Asphalt cost price adjust | calc | 4 | — | $1.00 | $1.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Erosion/Water Pollution Control | est | 4 | — | $1.00 | $1.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Roadway Excavation Incl. Haul | cubic yard | 4 | — | $30.00 | $30.00 – $60.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Project Temporary Traffic Control | ls | 4 | — | $4,000 | $2,500 – $58,334 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Mobilization | ls | 4 | — | $36,500 | $15,000 – $134,000 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Hot mix asphalt class. 1/2 in. pg 64-22 | ton | 3 | — | $90.00 | $90.00 – $151.78 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Gravel Borrow Incl. Haul | ton | 3 | — | $20.00 | $20.00 – $49.29 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Roadside Cleanup | est | 3 | — | $1.00 | $1.00 | Oct 11, 2016, Open bid tab, contract 38055 ↗ |
| High Visibility Fence | linear foot | 3 | — | $6.00 | $1.00 – $6.00 | Oct 11, 2016, Open bid tab, contract 38055 ↗ |
| ESC Lead | day | 3 | — | $50.00 | $25.00 – $400.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Remove of structure and obstruction | ls | 3 | — | $2,500 | $2,500 – $27,000 | Oct 11, 2016, Open bid tab, contract 38055 ↗ |
| Permanent Signing | ls | 3 | — | $3,000 | $1,000 – $3,465 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| High Visibility Silt Fence | linear foot | 3 | — | $4.40 | $4.40 – $9.46 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Paint Line | linear foot | 3 | — | $0.8 | $0.74 – $2.25 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Crushed Surfacing Base Course | ton | 3 | — | $30.00 | $30.00 – $78.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Inlet Protection | each | 3 | — | $50.00 | $50.00 – $60.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Field Office Building | ls | 2 | — | $10,000 | $8,000 – $10,000 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Rock FOR Rock Wall | ton | 2 | — | $100.00 | $100.00 – $210.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Bark or wood chip mulching | acre | 2 | — | $23,000 | $23,000 – $42,000 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Force Account | est | 2 | — | $1.00 | $1.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Locking Solid Metal Cover and Frame for Catch Basin | each | 2 | — | $380.00 | $380.00 – $824.17 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Pedestrian Control AND Protection | ls | 2 | — | $2,500 | $2,500 – $3,217 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Cement concrete. pedestrian curb | linear foot | 2 | — | $67.00 | $27.55 – $67.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Sod install | square yard | 2 | — | $14.60 | $14.60 – $16.38 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Topsoil Type A | cubic yard | 2 | — | $42.00 | $25.00 – $42.00 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Streambed Sediment | ton | 2 | — | $130.00 | $82.00 – $130.00 | Oct 11, 2016, Open bid tab, contract 38055 ↗ |
| Beam Guardrail Type 31 Non-flared Terminal | each | 2 | — | $2,300 | $2,300 – $4,450 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Shoring or extra excavation class. a | ls | 2 | — | $600.00 | $600.00 – $5,000 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Quarry Spalls | ton | 2 | — | $21.50 | $21.50 – $108.35 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Roadway Surveying | ls | 2 | — | $5,000 | $5,000 – $7,700 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Structure Surveying | ls | 2 | — | $14,000 | $6,200 – $14,000 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Adjust Catch Basin | each | 2 | — | $325.00 | $325.00 – $561.19 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Record Drawings | ls | 2 | — | $5,000 | $2,500 – $5,000 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Stabilized Construction Entrance | square yard | 2 | — | $50.00 | $20.00 – $50.00 | Oct 11, 2016, Open bid tab, contract 38055 ↗ |
| Clearing AND Grubbing | acre | 2 | — | $14,000 | $14,000 – $41,386 | Feb 16, 2017, Open bid tab, contract 41258 ↗ |
| Property Restoration | est | 1 | — | $1.00 | $1.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Cement Concrete Pedestrian Curb | linear foot | 1 | — | $27.00 | $27.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Cement Concrete Traffic Curb And Gutter | linear foot | 1 | — | $27.00 | $27.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |
| Hot mix asphalt for pavement repair hot mix asphalt class 1/2 in pg 64-22 | ton | 1 | — | $225.00 | $225.00 | Jan 9, 2018, Open bid tab, contract 49383 ↗ |