Earthwork · awarded bid prices
Clearing AND Grubbing: cost per acre in Washington
The median awarded price is $25,000 per acre, from 40 winning bids on 40 public projects in Washington (2024–2026). Half of the awarded prices fall between $13,250 and $51,416.
Cost by state › Washington › Clearing AND Grubbing
Winning bids only, as printed in the agencies' bid tabulations (Cowlitz County, WSDOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $22,000 in 2021 to $16,000 in 2026 (-27%).
| Year | Median per acre | Winning bids |
|---|---|---|
| 2021 | $22,000 | 25 |
| 2022 | $20,000 | 23 |
| 2023 | $30,000 | 21 |
| 2024 | $25,500 | 14 |
| 2025 | $40,000 | 15 |
| 2026 | $16,000 | 11 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Nov 4, 2026 | WSDOT | 10 ACRE | $33,000 | line 2 ↗ |
| Aug 19, 2026 | WSDOT | 48.3 ACRE | $3,250 | line 2 ↗ |
| Jul 22, 2026 | WSDOT | 0.94 ACRE | $20,966 | line 2 ↗ |
| Jul 15, 2026 | WSDOT | 1.6 ACRE | $2,605 | line 2 ↗ |
| Jul 8, 2026 | WSDOT | 0.14 ACRE | $16,000 | line 2 ↗ |
See every awarded price for this item, in all states, on the Clearing AND Grubbing item page.
Clearing AND Grubbing in other states
- Iowa: median $10,000 (357 bids)
- Missouri: median $7,228 (190 bids)
- Mississippi: median $7,800 (42 bids)
- Virginia: median $39,756 (29 bids)
- Indiana: median $26,152 (25 bids)
Related items in Washington
- Roadway Excavation Incl. Haul: $50.00 per cubic yard
- Structure Excavation Class B Incl. Haul: $30.00 per cubic yard
- Embankment Compaction: $11.00 per cubic yard
Free account: new awarded prices for this item show on your watchlist.