Earthwork · awarded bid prices · Collin County
Trench Excavation Protection: cost per linear foot in Collin County, TX
The median awarded price is $8.68 per linear foot, from 18 winning bids on 18 public projects in Collin County, TX (2024–2026). Half of the awarded prices fall between $5.00 and $14.56.
Cost by state › Texas › Collin County › Trench Excavation Protection
Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1.12 in 2022 to $8.00 in 2026 (+611%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2022 | $1.12 | 6 |
| 2023 | $15.00 | 7 |
| 2024 | $6.17 | 6 |
| 2025 | $15.00 | 6 |
| 2026 | $8.00 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Nov 4, 2026 | TxDOT | 19740 LF | $1.00 | line 26 ↗ |
| Oct 6, 2026 | TxDOT | 460 LF | $15.00 | line 28 ↗ |
| Aug 6, 2026 | TxDOT | 703 LF | $5.00 | line 40 ↗ |
| Jul 2, 2026 | TxDOT | 307 LF | $12.00 | line 33 ↗ |
| Jul 1, 2026 | TxDOT | 82 LF | $11.00 | line 20 ↗ |
See every awarded price for this item on the Trench Excavation Protection item page.
Related items in Collin County
- Excavation (Roadway): $17.20 per cubic yard
- Compost Manuf Topsoil (4"): $2.00 per square yard
- Excav (Roadway): $19.50 per cubic yard
- CEM Stabil Bkfl: $245.00 per cubic yard
- Flowable Backfill: $272.50 per cubic yard
- Backfill (TY A or B): $300.00 per station
- Blading: $300.00 per station