Earthwork · awarded bid prices · Collin County
Flowable Backfill: cost per cubic yard in Collin County, TX
The median awarded price is $272.50 per cubic yard, from 14 winning bids on 14 public projects in Collin County, TX (2024–2026). Half of the awarded prices fall between $250.00 and $375.00.
Cost by state › Texas › Collin County › Flowable Backfill
Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $300.00 in 2022 to $300.00 in 2025 (+0%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2022 | $300.00 | 5 |
| 2024 | $270.00 | 5 |
| 2025 | $300.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Oct 6, 2026 | TxDOT | 44 CY | $250.00 | line 27 ↗ |
| Aug 6, 2026 | TxDOT | 127 CY | $250.00 | line 39 ↗ |
| Jul 2, 2026 | TxDOT | 30 CY | $250.00 | line 32 ↗ |
| Jul 1, 2026 | TxDOT | 35 CY | $280.00 | line 19 ↗ |
| Nov 12, 2025 | TxDOT | 5 CY | $300.00 | line 3 ↗ |
The same item across Texas: statewide figures. See every awarded price for this item on the Flowable Backfill item page.
Related items in Collin County
- Excavation (Roadway): $17.20 per cubic yard
- Compost Manuf Topsoil (4"): $2.00 per square yard
- Excav (Roadway): $19.50 per cubic yard
- Trench Excavation Protection: $8.68 per linear foot
- CEM Stabil Bkfl: $245.00 per cubic yard
- Backfill (TY A or B): $300.00 per station
- Blading: $300.00 per station