Construction unit costs in South Carolina

Median awarded unit prices for the 43 most-bid items on South Carolina public projects, from winning bids in agency bid tabulations.

Cost by state › South Carolina

ItemPerMedianMiddle halfWinning bids
Permanent Yellow Pavement Markers Bi-dir.- 4"x4"each$6.50$4.50 – $8.00487
Permanent Construction Signs (Ground Mounted)square foot$6.50$5.95 – $7.40469
Liquid Asphalt Binder PG64-22ton$685.00$640.00 – $727.26464
Maintenance Stoneton$80.00$55.00 – $110.00415
Borrow Excavationcubic yard$50.00$35.25 – $69.40409
Milling Existing Asphalt Pavement (Variable)square yard$10.01$6.51 – $16.00377
4" Yellow Solid Lines(Pvt.Edge Lines) THERMO-90 Mil.linear foot$0.5$0.45 – $0.75358
24" White Solid Lines (Stop/Diag Lines)-THERMO.-125 MILlinear foot$10.00$8.40 – $13.00353
4" White Solid Lines (Pvt. Edge Lines) Thermo.- 90 Mil.linear foot$0.5$0.45 – $0.75350
4"Yellow Solid Line(Pvt.Edge&No Passing Zone)-Fast Dry Paintlinear foot$0.135$0.11 – $0.15330
4" White Solid Lines (Pvt. Edge Lines)-Fast Dry Paintlinear foot$0.135$0.11 – $0.15328
Milled-in Rumble Stripmile$712.50$500.00 – $1,042324
24" White Solid Lines (Stop/Diagonal Lines)-Fast Dry Paintlinear foot$1.00$0.5 – $1.50321
4" White Broken Lines -(Gaps Excluded)-Fast Dry Paintlinear foot$0.13$0.11 – $0.15296
Permanent Clear Pavement Markers- Mono-dir.- 4"x4"each$6.00$4.25 – $7.18296
Permanent Grassing for Non-permitted Resurfacing Projectsacre$3,360$3,175 – $4,000293
4" White Broken Lines(Gaps Excl.)Thermoplastic- 90 Mil.linear foot$0.65$0.47 – $0.85284
4" Yellow Broken Lines(Gaps Exc) - Fast Dry Paintlinear foot$0.13$0.11 – $0.15273
Full Depth Asph. Pav. Patching 8" Unifsquare yard$80.00$72.00 – $100.00262
Unclassified Excavationcubic yard$36.58$25.00 – $54.00260
Removal & Disposal of Existing Pavementsquare yard$36.00$24.89 – $45.75246
4" Yellow Broken Lines(Gaps Exc)Thermoplastic - 90 Mil.linear foot$0.5$0.445 – $0.55243
8" White Solid Lines Thermoplastic - 125 Mil.linear foot$3.00$2.50 – $3.70243
White Single Arrows (Lt, Strght, RT) THERMO.-125 Mil.each$100.00$75.00 – $125.00233
Detectable Warning Materialsquare foot$55.00$45.00 – $65.00228
Pedestrian Ramp Constructionsquare yard$160.00$125.50 – $214.00225
Milling Existing Asphalt Pavement 2.0"square yard$3.00$2.40 – $4.50218
Furnish & Install 1.0" Schedule 80 PVC Conduitlinear foot$20.00$14.90 – $21.50217
Silt Fencelinear foot$3.88$3.25 – $4.75210
Hauling of Excavated Shoulder Materialstation$70.80$51.00 – $91.21208
Excavation for Shoulder Pavingstation$61.72$42.50 – $110.00208
White Word Message"Only" - Thermoplastic - 125 Mil.each$100.00$75.00 – $150.00207
White Single Arrow (Left, Straight, Right)-Fast Dry Painteach$15.00$10.00 – $25.00204
Premash Type T TL3 Leading 50'each$3,300$2,940 – $3,898201
Sawcut for Loop Detectorlinear foot$9.61$8.67 – $12.00200
Furnish & Instl NO. 14 Copper Wire,1-Conductor for Loop Wirelinear foot$1.19$0.6 – $1.81200
MT3 Leading End Treatment TL3each$3,400$3,100 – $3,817200
HMA Shoulder Widening Courseton$80.45$74.59 – $91.00198
Mowingacre$466.61$400.00 – $600.00144
Traffic Controleach$875.00$500.00 – $1,67542
Temporary Concrete Barrierlinear foot$49.00$43.70 – $50.0025
Law Enforcement Officerhour$50.00$50.00 – $50.0024
Structural Steelpound$16.00$10.88 – $20.0016