4 inch yellow broken line(gaps excavation) - fast dry paint: cost per linear foot in South Carolina

Listed by the agency as “4" Yellow Broken Lines(Gaps Exc) - Fast Dry Paint”.

The median awarded price is $0.13 per linear foot, from 273 winning bids on 273 public projects in South Carolina (2023–2026). Half of the awarded prices fall between $0.11 and $0.15.

Cost by state › South Carolina › 4" Yellow Broken Lines(Gaps Exc) - Fast Dry Paint

$0.13median per linear foot
$0.11 – $0.15middle half (25th–75th percentile)
273winning bids, 273 source documents
2023–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (SCDOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $0.12 in 2021 to $0.12 in 2026 (+0%).

YearMedian per linear footWinning bids
2021$0.1289
2022$0.13113
2023$0.1580
2024$0.14125
2025$0.1385
2026$0.1241

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Aug 11, 2026SCDOT1980 LF$0.15Open bid tab, contract 1477330 ↗
Aug 11, 2026SCDOT11550 LF$0.13Open bid tab, contract 3577310 ↗
Aug 11, 2026SCDOT4120 LF$0.15Open bid tab, contract 4277290 ↗
Aug 11, 2026SCDOT3749 LF$0.12Open bid tab, contract 8876590 ↗
Aug 11, 2026SCDOT7125 LF$0.15Open bid tab, contract 8876600 ↗

See every awarded price for this item, in all states, on the 4" Yellow Broken Lines(Gaps Exc) - Fast Dry Paint item page.

Related items in South Carolina

Free account: new awarded prices for this item show on your watchlist.


We record the address to count report readers; the link opens right after.