| Permanent construction sign (ground mounted) | square foot | $6.50 | $6.00 – $7.40 | 21 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Permanent yellow pavement markers bi-dir.- 4 inchx4 inch | each | $7.50 | $6.80 – $8.44 | 20 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Liquid Asphalt Binder PG64-22 | ton | $707.50 | $648.75 – $725.00 | 20 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Milling existing asphalt pavement 2.0 inch | square yard | $3.95 | $2.96 – $6.22 | 20 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 4 inch yellow solid line(pvt.edge line) thermoplastic-90 mil. | linear foot | $0.825 | $0.502 – $1.29 | 18 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 24 inch white solid line (stop/diag line)-thermoplastic.-125 mil | linear foot | $9.43 | $8.56 – $13.88 | 18 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Furnish & install 1.0 inch schedule 80 pvc conduit | linear foot | $20.00 | $15.30 – $20.12 | 16 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 4 inch white solid line (pvt. edge line) thermoplastic.- 90 mil. | linear foot | $0.725 | $0.5 – $1.16 | 16 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Maintenance Stone | ton | $95.00 | $67.50 – $134.25 | 15 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Permanent clear pavement markers- mono-dir.- 4 inchx4 inch | each | $7.00 | $6.50 – $7.95 | 15 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 4 inch white broken line(gaps excl.)thermoplastic- 90 mil. | linear foot | $0.8 | $0.575 – $1.05 | 15 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 24 inch white solid line (stop/diagonal line)-fast dry paint | linear foot | $1.02 | $0.663 – $1.46 | 14 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 4 inch white solid line (pvt. edge line)-fast dry paint | linear foot | $0.15 | $0.14 – $0.17 | 13 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Milled-in Rumble Strip | mile | $600.00 | $570.00 – $2,000 | 13 | Nov 12, 2025, Open bid tab, contract 2373450 ↗ |
| White single arrows (lt, strght, rt) thermoplastic.-125 mil. | each | $100.00 | $78.95 – $110.00 | 13 | Nov 12, 2025, Open bid tab, contract 2370000 ↗ |
| Pedestrian Ramp Construction | square yard | $207.00 | $180.00 – $235.90 | 13 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| 8 inch white solid line thermoplastic - 125 mil. | linear foot | $2.75 | $2.50 – $3.00 | 13 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Detectable Warning Material | square foot | $50.00 | $46.00 – $75.00 | 13 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |
| Borrow Excavation | cubic yard | $60.00 | $51.15 – $90.00 | 13 | Apr 14, 2026, Open bid tab, contract 2372300 ↗ |