Earthwork · awarded bid prices · Greene County
Class 3 Excavation: cost per cubic yard in Greene County, MO
The median awarded price is $50.50 per cubic yard, from 12 winning bids on 9 public projects in Greene County, MO (2024–2026). Half of the awarded prices fall between $32.40 and $93.00.
Cost by state › Missouri › Greene County › Class 3 Excavation
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $30.00 in 2023 to $51.00 in 2024 (+70%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2023 | $30.00 | 13 |
| 2024 | $51.00 | 7 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Mar 20, 2026 | MoDOT | 642 CUYD | $43.00 | Open the source page, contract 260320-G01 |
| Oct 17, 2025 | MoDOT | 3082 CUYD | $8.03 | Open the source page, contract 251017-G02 |
| Oct 17, 2025 | MoDOT | 42 CUYD | $160.00 | Open the source page, contract 251017-G04 |
| Aug 15, 2025 | MoDOT | 73 CUYD | $50.00 | Open the source page, contract 250815-G02 |
| Mar 14, 2025 | MoDOT | 211 CUYD | $88.00 | Open the source page, contract 250314-G03 |
The same item across Missouri: statewide figures. See every awarded price for this item on the Class 3 Excavation item page.
Related items in Greene County
- Rock Ditch Check: $15.75 per linear foot
- Unclassified Excavation: $12.13 per cubic yard
- Compacting Embankment: $6.00 per cubic yard
- Rock Lining: $149.50 per cubic yard