Earthwork · awarded bid prices · Greene County
Compacting Embankment: cost per cubic yard in Greene County, MO
The median awarded price is $6.00 per cubic yard, from 23 winning bids on 17 public projects in Greene County, MO (2021–2025). Half of the awarded prices fall between $4.44 and $8.30.
Cost by state › Missouri › Greene County › Compacting Embankment
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $4.99 in 2023 to $6.00 in 2024 (+20%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2023 | $4.99 | 12 |
| 2024 | $6.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Oct 17, 2025 | MoDOT | 5224 CUYD | $6.37 | Open the source page, contract 251017-G02 |
| Oct 17, 2025 | MoDOT | 5264 CUYD | $8.50 | Open the source page, contract 251017-G04 |
| Aug 15, 2025 | MoDOT | 46 CUYD | $100.00 | Open the source page, contract 250815-G02 |
| Mar 14, 2025 | MoDOT | 12711 CUYD | $7.70 | Open the source page, contract 250314-G03 |
| Dec 13, 2024 | MoDOT | 12218 CUYD | $6.00 | Open the source page, contract 241213-G02 |
The same item across Missouri: statewide figures. See every awarded price for this item on the Compacting Embankment item page.
Related items in Greene County
- Rock Ditch Check: $15.75 per linear foot
- Unclassified Excavation: $12.13 per cubic yard
- Rock Lining: $149.50 per cubic yard
- Class 3 Excavation: $50.50 per cubic yard