Skip to contentSkip to content
Hubstake
Earthwork 417105

Class 3 Excavation

Unit CY · Lettings Jun 19, 2014 – Apr 9, 2015 · 1 agencies

22Winning bids
1Agencies
Jun 19, 2014 – Apr 9, 2015Letting period
Median winning unit price
Standard 22 winning bids

$60.00/ CY

Winning bids
Source documents
22
10

Winning bids only, as awarded. Nominal dollars. How we compute this

Where the number comes from

One of the 22 winning bids behind that median, with the agency’s own document one click away.

Agency
MDOT SHA · St. Mary'S, Maryland
Letting
Oct 9, 2014
Quantity
624.000 CY
Contractor
ANCHOR CONSTRUCTION
Winning price
$65.31 / CY
Open bid tab, contract SM3665180 ↗14_10_16.SM3665180 - WEB-TABS.tab.pdf

Price distribution

Free account

The spread behind this median — every observed price, and where the middle half sits. A free account opens it.

Create a free account Sign in

The observation table

Free account

All 22 winning bids behind this median, each with its agency, letting date, quantity and the document it came from. A free account opens it.

Create a free account Sign in

More with Estimator

Split by who let the work

State DOT, city and developer prices side by side.

Compared across agencies

What each agency has paid for this item.

Median by quarter

How this item has priced over time.

See what Estimator adds →