Construction unit costs in Hartford County, CT

Median awarded unit prices for 40 items on public projects in Hartford County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Connecticut › Hartford County

ItemPerMedianMiddle halfWinning bidsLatest source document
Traffic Drumeach$75.00$52.25 – $85.7538Jul 29, 2026, line 1780 ↗
Trafficperson (Uniformed Flagger)hour$68.75$59.75 – $75.5032Jul 29, 2026, line 1730 ↗
Barricade Warning Lights - High Intensityday$1.00$0.812 – $1.0030Jul 29, 2026, line 1770 ↗
Remote Control Changeable Message Signday$38.00$25.00 – $61.0029Jul 29, 2026, line 1860 ↗
42'' Traffic Coneeach$45.00$41.88 – $49.2528Jul 29, 2026, line 1820 ↗
Earth Excavationcubic yard$43.50$22.75 – $73.7526Jul 29, 2026, line 0120 ↗
Construction Barricade Type IIIeach$159.43$146.25 – $173.7526Jul 29, 2026, line 1790 ↗
Cut asphalt concrete pavementlinear foot$4.50$3.02 – $6.0026Jul 29, 2026, line 0180 ↗
Arrow Boardday$31.00$15.00 – $40.0025Jul 29, 2026, line 1850 ↗
Construction sign ** see special provisions **square foot$30.00$20.00 – $40.0025Jul 29, 2026, line 2000 ↗
Processed Aggregateton$94.50$63.75 – $124.0724Jul 29, 2026, line 0390 ↗
Metal Beam Rail (R-b Mash)linear foot$30.91$29.80 – $35.0024Jul 29, 2026, line 1320 ↗
Sign Face - Sheet Aluminum (Type XI Retroreflective Sheeting) ** See Special Provisions **square foot$85.00$74.25 – $116.2524Jul 29, 2026, line 1900 ↗
Truck-mounted or Trailer- Mounted Impact Attenuatorhour$117.50$40.00 – $147.7524Jul 29, 2026, line 2200 ↗
Pre-warning Vehicle ** See Special Provisions **hour$78.50$35.00 – $125.0024Jul 29, 2026, line 3520 ↗
Non-tracking Asphalt Tack Coatgallon$12.00$9.75 – $22.0023Jul 29, 2026, line 0480 ↗
Furnishing and Placing Topsoilsquare yard$13.00$8.82 – $19.5923Jul 29, 2026, line 1600 ↗
Sediment control systemlinear foot$6.86$6.00 – $7.0022Jul 29, 2026, line 0340 ↗
Fine milling of asphalt concrete (0 inch to 4 inch)square yard$5.50$4.00 – $15.2322Jul 29, 2026, line 0500 ↗
Hot mix asphalt s0.5ton$272.91$151.25 – $400.0021Jul 29, 2026, line 0460 ↗
Processed Aggregate Basecubic yard$69.00$54.38 – $127.5020Jul 29, 2026, line 0380 ↗
Hot mix asphalt s0.375ton$188.40$143.25 – $264.7520Jul 29, 2026, line 0420 ↗
Remove Metal Beam Raillinear foot$4.20$3.33 – $5.0019Jul 29, 2026, line 1340 ↗
Temporary Traffic Barrierlinear foot$80.00$52.50 – $106.7518Jul 29, 2026, line 1230 ↗
Trench and backfillinglinear foot$49.36$32.19 – $61.0018Jul 22, 2026, line 0640 ↗
Concrete Sidewalksquare foot$25.00$16.50 – $40.7518Jul 29, 2026, line 1490 ↗
Remove of pavement markingsquare foot$2.05$1.25 – $4.0017Jul 29, 2026, line 1960 ↗
Granular Fillcubic yard$111.00$75.00 – $150.0017Jul 29, 2026, line 0300 ↗
Sediment Control System at Catch Basin ** See Special Provisions **each$150.00$115.00 – $275.0017Jul 29, 2026, line 0350 ↗
Epoxy resin pavement marking, symbols and legendssquare foot$6.75$5.53 – $8.5017Jul 29, 2026, line 1940 ↗
Deformed Steel Bars - Galvanizedpound$2.77$2.50 – $3.8316Jul 29, 2026, line 0830 ↗
Sign Face - Sheet Aluminum (Type IX Retroreflective Sheeting) ** See Special Provisions **square foot$85.00$69.00 – $92.5015Jul 29, 2026, line 1890 ↗
Temporary Sand Barrel (400 Lb.)each$500.00$443.50 – $556.0015Jul 29, 2026, line 3420 ↗
Temporary Sand Barrel (700 Lb.)each$500.00$450.00 – $534.5015Jul 29, 2026, line 3430 ↗
Temporary Sand Barrel (1400 Lb.)each$500.00$450.00 – $563.5015Jul 29, 2026, line 3440 ↗
Temporary Sand Barrel (2100 Lb.)each$500.00$450.00 – $600.0015Jul 29, 2026, line 3450 ↗
Construction signsquare foot$25.12$14.68 – $34.0015Jul 22, 2026, line 0710 ↗
Test Pit ** See Special Provisions **each$2,440$1,550 – $2,92514Jul 29, 2026, line 0160 ↗
Hot-applied paint pavement marking 4'' whitelinear foot$0.35$0.275 – $0.5412Dec 10, 2025, line 0660 ↗
Hot-applied paint pavement marking 4'' yellowlinear foot$0.39$0.295 – $0.5412Jan 7, 2026, line 0730 ↗