Other · awarded bid prices · Hartford County
Pre-warning Vehicle ** See Special Provisions **: cost per hour in Hartford County, CT
The median awarded price is $78.50 per hour, from 24 winning bids on 24 public projects in Hartford County, CT (2024–2026). Half of the awarded prices fall between $35.00 and $125.00.
Cost by state › Connecticut › Hartford County › Pre-warning Vehicle ** See Special Provisions **
Winning bids only, as printed in the agencies' bid tabulations (CTDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $77.50 in 2021 to $75.00 in 2026 (-3%).
| Year | Median per hour | Winning bids |
|---|---|---|
| 2021 | $77.50 | 6 |
| 2022 | $100.00 | 5 |
| 2025 | $78.50 | 12 |
| 2026 | $75.00 | 8 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 29, 2026 | CTDOT | 900 hr | $100.00 | line 3520 ↗ |
| Jul 22, 2026 | CTDOT | 640 hr | $35.00 | line 0830 ↗ |
| Jul 1, 2026 | CTDOT | 250 hr | $125.00 | line 0710 ↗ |
| Apr 1, 2026 | CTDOT | 1550 hr | $20.00 | line 1360 ↗ |
| Mar 25, 2026 | CTDOT | 5000 hr | $50.00 | line 0540 ↗ |
The same item across Connecticut: statewide figures. See every awarded price for this item on the Pre-warning Vehicle ** See Special Provisions ** item page.
Related items in Hartford County
- Arrow Board: $31.00 per day
- Deformed Steel Bars - Galvanized: $2.77 per pound
- Temporary Sand Barrel (400 Lb.): $500.00 per each
- Temporary Sand Barrel (700 Lb.): $500.00 per each
- Temporary Sand Barrel (1400 Lb.): $500.00 per each
- Temporary Sand Barrel (2100 Lb.): $500.00 per each
- Test Pit ** See Special Provisions **: $2,440 per each