Construction unit costs in Various County, CT

Median awarded unit prices for 34 items on public projects in Various County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Connecticut › Various County

ItemPerMedianMiddle halfWinning bidsLatest source document
Construction signsquare foot$10.00$10.00 – $17.6240Sep 23, 2026, line 1510 ↗
Sign Face - Sheet Aluminum (Type XI Retroreflective Sheeting) ** See Special Provisions **square foot$56.50$42.88 – $63.0032Sep 23, 2026, line 1460 ↗
Traffic Drumeach$40.00$20.00 – $84.0031Sep 23, 2026, line 0480 ↗
Epoxy resin pavement marking, symbols and legendssquare foot$8.00$5.80 – $10.0029Sep 23, 2026, line 1490 ↗
Remove of pavement markingsquare foot$5.00$2.63 – $6.0028Sep 23, 2026, line 1500 ↗
Traffic Coneeach$20.00$13.50 – $22.5028Sep 23, 2026, line 0470 ↗
42'' Traffic Coneeach$32.50$20.00 – $50.0024Jun 17, 2026, line 0570 ↗
Truck-mounted or Trailer- Mounted Impact Attenuatorhour$75.00$35.00 – $112.5023Jun 17, 2026, line 0680 ↗
Sign Face - Sheet Aluminum (Type IX Retroreflective Sheeting) ** See Special Provisions **square foot$59.50$45.00 – $65.0021Sep 23, 2026, line 1450 ↗
2'' Rigid Metal Conduit Under Roadwaylinear foot$24.10$21.00 – $26.7021Sep 23, 2026, line 0680 ↗
1 Way Pedestrian Signal Pole Mounted ** See Special Provisions **each$1,015$914.00 – $1,11421Sep 23, 2026, line 0920 ↗
Asphalt concrete patch - partial deep ** see special provisions **square yard$120.00$87.00 – $186.0021Feb 18, 2026, line 0080 ↗
Material for Tack Coatgallon$32.00$26.25 – $60.0021Aug 6, 2025, line 1770 ↗
1 Way Pedestrian Signal Pedestal Mounted ** See Special Provisions **each$871.50$688.00 – $963.7520Sep 23, 2026, line 0930 ↗
4 inch yellow epoxy resin pavement markinglinear foot$1.00$0.975 – $2.2519Sep 23, 2026, line 1480 ↗
Remote Control Changeable Message Signday$42.00$25.00 – $50.0017Jun 17, 2026, line 0590 ↗
Barricade Warning Lights - High Intensityday$1.00$1.00 – $1.0016Jun 17, 2026, line 0520 ↗
Construction Barricade Detectable ** See Special Provisions **each$271.50$145.50 – $282.7516Aug 20, 2025, line 0360 ↗
Trench and backfillinglinear foot$55.00$39.13 – $71.0015Sep 23, 2026, line 0510 ↗
4 inch white epoxy resin pavement markinglinear foot$1.00$1.00 – $2.0015Sep 23, 2026, line 1470 ↗
Asphalt concrete lip curbinglinear foot$39.00$24.50 – $65.5015Sep 23, 2026, line 0240 ↗
2'' Rigid Metal Conduit in Trenchlinear foot$21.50$19.25 – $25.4314Sep 23, 2026, line 0650 ↗
Modify Existing Controller ** See Special Provisions **each$2,833$2,392 – $4,16414Aug 19, 2026, line 0760 ↗
Concrete Sidewalksquare foot$41.00$35.25 – $73.5014Aug 19, 2026, line 0120 ↗
Arrow Boardday$15.00$10.00 – $39.2514Jun 17, 2026, line 0580 ↗
Processed Aggregateton$142.00$80.00 – $200.0013Sep 23, 2026, line 0130 ↗
Traffic Control Foundation- Pedestal-type Ieach$799.00$715.00 – $1,10013Sep 23, 2026, line 0570 ↗
Furnishing and Placing Topsoilsquare yard$17.00$11.50 – $24.2512Sep 23, 2026, line 0370 ↗
Cut asphalt concrete pavementlinear foot$5.50$3.90 – $10.7512Sep 23, 2026, line 0070 ↗
Radar Detector ** See Special Provisions **each$16,182$14,400 – $17,64612Sep 23, 2026, line 1100 ↗
360- Degree Camera Assembly ** See Special Provisions **each$4,582$3,671 – $6,49012Sep 23, 2026, line 1110 ↗
360-Degree Video Detection Processor ** See Special Provisions **each$19,798$18,772 – $22,62712Sep 23, 2026, line 1120 ↗
7 Conductor NO. 14 Cablelinear foot$3.15$2.96 – $3.6112Sep 23, 2026, line 1200 ↗
23 AWG 4 Twisted Pair Category 6 Cable ** See Special Provisions **linear foot$3.50$3.14 – $4.1412Sep 23, 2026, line 1250 ↗