Steel Reinforcement for Bridge Superstructure, Sta. 4+43, Approx. 118, 415 Lbs.
Median lump-sum amount
Thin 4 winning bids≈$67,700per contractLow confidence
- Winning bids
- 4
- Source documents
- 1
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 4 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ALDOT · Alabama
- Letting
- Dec 8, 2000
- Quantity
- 1 LS
- Contractor
- Tanner Construction Company, Inc.
- Winning price
- $44,998 / LS
What’s behind $67,700
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 4 bids charted, so you can see clusters and outliers.
4 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Related items
Other structures items priced per LS, ranked by how much evidence each has.
- NS Bridge Prefabricated Steel Truss Superstructure$720,0008 bids
- Clean Steel Bridge, QP-2, Bridge No. 1$130,075104 bids
- Paint Steel Bridge, Bridge No. 1$36,00099 bids
- Clean Steel Bridge, QP-2, Bridge No. 2$110,00083 bids
- Paint Steel Bridge, Bridge No. 2$34,50083 bids
- Structural Steel, Bridge No. 1$320,47263 bids
- Clean Structural Steel (Existing Bridge)$316,60057 bids
- Paint Structural Steel (Existing Bridge)$281,30556 bids
4 observations
1 agency in 1 state · lettings Dec 8, 2000
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.