Rock Bolts 25 Kip
One winning unit price
Single 1 winning bid$55.00/ LF
- Letting
- Jan 9, 2003
- Quantity
- 2085 LF
- Agency
- WSDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WSDOT · Douglas, Washington
- Letting
- Jan 9, 2003
- Quantity
- 2085 LF
- Contractor
- ONE WAY Construction, Inc.
- Winning price
- $55.00 / LF
What’s behind $55.00
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other earthwork items priced per LF, ranked by how much evidence each has.
- Rock Bolt 25 Kip$60.003 bids
- Rock Bolt 50 Kip$1104 bids
- Rock Bolts$70.003 bids
- Pre-boring Rock or Consolidated$190248 bids
- Drilled Shaft with Rock Excavation - 42" Diameter$1,44387 bids
- Core Drilling for Piles(Rock)$30848 bids
- Drilled Shaft with Rock Excavation - 48" Diameter$1,46143 bids
- Cored Hole in Rock, 24 in$45539 bids
1 observation
1 agency in 1 state · lettings Jan 9, 2003
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.