Removing Existing Temporary Concrete Barrier
One winning unit price
Single 1 winning bid$27.00/ LF
- Letting
- Nov 20, 2019
- Quantity
- 75 LF
- Agency
- WSDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WSDOT · Jefferson, Washington
- Letting
- Nov 20, 2019
- Quantity
- 75 LF
- Contractor
- Interwest Construction, Inc.
- Winning price
- $27.00 / LF
What’s behind $27.00
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other paving items priced per LF, ranked by how much evidence each has.
- Concrete Barrier Temporary Precast$10.001,569 bids
- Temporary Concrete Barrier$37.30280 bids
- Concrete Safety Barrier (Type F3) (Temporary)$29.50228 bids
- Removing Concrete Barrier$17.75198 bids
- Concrete Safety Barrier (Type F3) (Temporary - Relocate)$9.00192 bids
- Temporary Conc. Barrier$13.25395 bids
- Concrete Barrier Transition$916389 bids
- Concrete Barrier Temp Precast$8.00351 bids
1 observation
1 agency in 1 state · lettings Nov 20, 2019
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.