Removing Cement Concrete Curb
One winning unit price
Single 1 winning bid$5.00/ LF
- Letting
- May 31, 2007
- Quantity
- 396.5 LF
- Agency
- WSDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WSDOT · Lincoln,Stevens, Washington
- Letting
- May 31, 2007
- Quantity
- 396.5 LF
- Contractor
- Frank Gurney, Inc.
- Winning price
- $5.00 / LF
What’s behind $5.00
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other paving items priced per LF, ranked by how much evidence each has.
- Removing Cement Conc. Curb$7.50181 bids
- Removing Cement Conc. Curb and Gutter$9.00169 bids
- Removing Curb & Gutter$6.003,092 bids
- Concrete Curb & Gutter 30-Inch$24.672,240 bids
- Concrete Curb & Gutter 4-Inch$36.581,308 bids
- Concrete Curb & Gutter 6-Inch$30.001,064 bids
- Removing Curb$8.18972 bids
- Concrete Curb Pedestrian$40.00946 bids
1 observation
1 agency in 1 state · lettings May 31, 2007
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.