Removing and Replacing Utility Vault
One winning bid
Single 1 winning bid$4,600per contract
- Letting
- Apr 13, 2005
- Quantity
- 1 LS
- Agency
- WSDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WSDOT · Yakima, Washington
- Letting
- Apr 13, 2005
- Quantity
- 1 LS
- Contractor
- MAX J. Kuney Company
- Winning price
- $4,600 / LS
What’s behind $4,600
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other other items priced per LS, ranked by how much evidence each has.
- Removing Old Structure (Station)$10,5001,367 bids
- Removing Old Structure over$30,000847 bids
- Removing (Item Description) 01.$2,500101 bids
- Generic Utility Item (Ls)$52,20083 bids
- Removing (Item Description)$2,00071 bids
- Removing (Item Description) 02.$3,00049 bids
- Utility Markers$1,47538 bids
- Removing Lighting Systems$21,15335 bids
1 observation
1 agency in 1 state · lettings Apr 13, 2005
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.