Remove Tubular Marker
One winning unit price
Single 1 winning bid$21.00/ EA
- Letting
- Apr 5, 2017
- Quantity
- 10 EACH
- Agency
- WSDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WSDOT · Spokane, Washington
- Letting
- Apr 5, 2017
- Quantity
- 10 EACH
- Contractor
- CPM Development Corporation
- Winning price
- $21.00 / EA
What’s behind $21.00
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other other items priced per EA, ranked by how much evidence each has.
- Remove Marker$30.00424 bids
- Removal of Snowplowable Reflective Marker$10.501,173 bids
- Right of Way Marker(Rebar and Cap)$130965 bids
- Right-of-way Marker$180809 bids
- Temp. Pave. Marker 1 Way$6.75486 bids
- Temp. Pave. Marker 2 Way$6.60388 bids
- Remove Energy Absorbing Terminal$375358 bids
- Remove Flared End Section (Ea)$517340 bids
1 observation
1 agency in 1 state · lettings Apr 5, 2017
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.