Median winning unit price
Very thin 2 winning bids≈$20.94/ LFLow confidence
- Winning bids
- 2
- Source documents
- 2
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 2 winning bids behind that median, with the agency’s own document one click away.
- Agency
- MDOT · Michigan
- Letting
- Apr 5, 2019
- Quantity
- 160 Ft
- Contractor
- D. J. McQuestion & Sons, Inc.
- Winning price
- $30.00 / LF
What’s behind $20.94
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 2 bids charted, so you can see clusters and outliers.
2 observations
Agency, county, letting date, quantity and the price as printed.
2 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Related items
Other structures items priced per LF, ranked by how much evidence each has.
- Pile, Steel, Furn and Driven, 12 Inch$31.30224 bids
- Pile, Steel, Furn and Driven, 14 Inch$44.0097 bids
- Test Pile, Dynamic, Production$80.00213 bids
- Test Pile, Indicator, Production$100188 bids
- Pile, Steel H Hp 12 x 53$80.00171 bids
- Pile Excavation Not in Soil$469150 bids
- Pile Excavation in Soil$365146 bids
- Pre-drilled Pile Holes$18582 bids
2 observations
1 agency in 1 state · lettings Jul 8, 2016 – Apr 5, 2019
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.