Mobilization (Unit Bid Amount May Not Exceed 5% of Subtotal) Contract Totals Date: 10/19/15 Arkansas State Highway and Transportation Department Page: 1 Bid Tabulation Summary Bids Opened for Job 070280 Letting Date: 10/13/15 NHPP-STPP-0070(33) County: Union Job Name: EL Dorado-hwy. 335 (S) Length: 5.039 Miles Routes: 167 Amount for Award Consideration (Per Job Special Provision “Site Use (A+C Method)”) Total Days Amount for Award Consideration Rank Vendor No./Name Bid Bid (Total Bid + Days Bid * $4,300) 1 YATE10 W.G. Yates & Sons Const. CO. $ 21,195,750.67 300 $ 22,485,750.67 2 JETA10 Jet Asphalt & Rock Co., Inc. $ 21,880,587.27 350 $ 23,385,587.27 3 EUTA10 Eutaw Construction Co., Inc. $ 22,102,626.86 325 $ 23,500,126.86 4 MCGE10 Mcgeorge Contracting Co., Inc. $ 23,392,420.96 215 $ 24,316,920.96 5 JAME20 James Construction Group, LLC $ 23,375,335.13 325 $ 24,772,835.13 Contract Amount Total % over Rank Vendor No./Name Bid Low Bid 1 YATE10 W.G. Yates & Sons Const. CO. $ 21,195,750.67 100.0000% 2 JETA10 Jet Asphalt & Rock Co., Inc. $ 21,880,587.27 103.2310% 3 EUTA10 Eutaw Construction Co., Inc. $ 22,102,626.86 104.2786% 4 MCGE10 Mcgeorge Contracting Co., Inc. $ 23,392,420.96 110.3637% 5 JAME20 James Construction Group, LLC $ 23,375,335.13 110.2831%
One winning bid
Single 1 winning bid$147,813per contract
- Letting
- Oct 13, 2015
- Quantity
- 1 L.S.
- Agency
- ARDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ARDOT · Stone, Arkansas
- Letting
- Oct 13, 2015
- Quantity
- 1 L.S.
- Contractor
- Pace Construction Co., LLC
- Winning price
- $147,813 / LS
What’s behind $147,813
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other paving items priced per LS, ranked by how much evidence each has.
- Clearing and Grubbing (Maximum Allowable Bid $ 10,000.00 per Hectare)(Approximately 2 Removing Concrete Driveway$20,0003 bids
- Coating Concrete Surfaces (At MP 126.100 (Bin 014156))$35,7443 bids
- Asphalt Air Void Pay Adjustment$1.00195 bids
- Asphalt Density Pay Adjustment$1.00192 bids
- Asphalt Pavement Smoothness$1.0033 bids
- Precast Reinf. Conc. Three Sided Structure NO. 1$141,57532 bids
- Precast Reinf. Conc. Three Sided Structure NO. 2$195,00010 bids
- Paving Construction Allowancc$150,0004 bids
1 observation
1 agency in 1 state · lettings Oct 13, 2015
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.